-_ -, <br />Response: <br />(1) The day we discovered the erosion at the super curve, the operator cut a temporary ditch <br />across the road to carry water into the designed culvert and prevent discharge into the <br />undisturbed area. Prior to the inspection, the ditch on the other side of the road had been cleaned <br />out and re-cut. <br />(2) and (3) P&M's representative. accompanied us on a tour of the locations. No immediate <br />response was appropriate. <br />(4) P&M had planned to clean out the ditches within 2 weeks of the inspection. Equipment was <br />brought on site to perform this maintenance of 23 June. <br />