Doc Date
6/2/1993
Doc Name
REQUEST FOR NOV ABATEMENT DATE EXTENSION GOLDEN EAGLE MINE PN C-81-013
From
BASIN RESOURCES INC
To
MLR
Violation No.
CV1993016
Media Type
D
Archive
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
3
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
Mr. Joseph Dudash <br />May 28, 1993 <br />Page 2 <br />cleaned and upgraded as per the requirements. An MR has been <br />submitted for Ditch 14. An extension for the cleaning of Ditch 17 <br />is requested due to the wet nature of the ditch. Culverts 4 and 5 <br />have been cleaned, culvert 7 has been removed, and an extension for <br />cleaning of the vent shaft access road culvert is requested. <br />NOV C-93-019 - Topsoil stockpile No. 4 has been fenced to eliminate <br />grazing. A extension is requested for the stockpile located along <br />the access road to the vent shaft. <br />NOV C-93-069 - An extension for the replacement of the Pond 003 <br />discharge pipe is requested. Repair work for Ditches 4, 5, 8, and <br />20 has been completed. An extension for repair of Ditch 7 is <br />requested. <br />NOV C-93-070 - Culvert 3 has been replaced with a designed 24 inch <br />culvert. Culvert 5 has been supplemented with a Reno Type Mattress <br />lined ditch of the type B cross section. An extension for sizing <br />Culvert 6 is requested. The culvert in Ciruela Canyon was <br />installed with the railroad and therefore not part of the sediment <br />control system for the mine. <br />Basin Resources is requesting an extension of the abatement <br />deadline for the above violations to June 11, 1993. The reason for <br />this extension request is due to a number of factors which include <br />the following: <br />1. Extremely wet weather over the past 60 days has prevented <br />earth work for many of the ditches and culverts. This weather has <br />also necessitated duplication of work which was conducted and than <br />needed to be reworked (e.g. cleaning of ditches). <br />2. Many of the items which need to be completed are extensive <br />activities and require significant effort and or specific <br />equipment. As these resources have been committed on active <br />projects which must be conducted under the NOVs, other NOV projects <br />are waiting to be completed. <br />3. The volume of work necessary to abate these NOVs is extensive <br />and has surpassed the ability of Basin's resources. As a result, <br />contractors have been hired to complete the work to the extent <br />possible. That is, there are only a few contractors in the area <br />which have the necessary insurance, equipment and experience to <br />complete the work. Basin is committed to utilize all of its <br />resources and qualified contractors to complete the abatement <br />activities as soon as possible. <br />4. One of Basin's key engineering staff left the operation in mid <br />May 1993 and is no longer available to complete the activities <br />which were assigned to him. <br />