operation will then shift to the azea immediately south of the existing access road in Cuts 3, 4 and 5. <br />The dewatering pump in these cuts will also deliver the water to the new Pond A in Cut 1. All subse- <br />quent cuts will deliver water to Ponds #3 and #4 at the south end of the permit area. <br />At any one time, three cuts will be active. The one in advance of the active cut will be stripped of <br />topsoil and will also have overburden removal activity. The active pit will have overburden removal <br />and gold beazing gravel mining. The cut behind the active pit will have overburden placement, re- <br />grading and topsoil placement. Reclamation plan details are described in Exhibit E. <br />The mining timetable for the gold operation is given below: <br />Mining Timetable -Gold Operation <br />Task # Description Time Needed <br />in months <br />1 Strip Initial overburden from Cut 1 and place to the north- <br />east. Regrade this northeast azea. 2.0 <br />2 Mine Cut 1. Create new Pond A. 0.5 <br />3 Mine Cut 2. Very little overburden. 1.0 <br />4 Create 8' gravel berm along Highway 9 ROW 0.5 <br />5 Create Ponds 1,2,3,4 on southwest corner of permit azea I.0 <br />6 Strip overburden from Cut 3 and place in Cut 1. Move <br />Pond A back to Cut 2 azea. 1.5 <br />7 Mine cuts 4-47 stripping and replacing topsoil & overbuy- <br />den in the previous cut. 64.5 <br />8 Backfill last cut with gravel from Highway 9 berm 1.5 <br />9 Remove all equipment from site 1.0 <br />10 Seed, mulch and place tree saplings in remaining reclaimed <br />azea 1.0 <br /> TOTAL ?? <br />Alma Placer 7/03 13 <br />