Laserfiche WebLink
The mining timetable for the gold operation is given below: <br />~' Mining Timetable -Gold Operation <br /> <br />Task # Description Time Needed <br />in months <br />1 Strip Initial overburden from Cut 1 and place to the <br />northeast. Regrade this northeast azea. 2.0 <br />2 Mine Cut 1. Create new Pond A. 0.5 <br />3 Mine Cut 2. Very little overburden. 1.0 <br />4 Create 8' gravel berm along Highway 9 ROW 0.5 <br />5 Create Ponds 1,2,3,4 on southwest corner of permit azea 1.0 <br />6 Strip overburden from Cut 3 and place in Cut 1. Move <br />Pond A back to Cut 2 azea. 1.5 <br />7 Mine cuts 4-47 stripping and replacing topsoil & <br />overburden in the previous cut. 64.5 <br />8 Backfill last cut with gravel from Highway 9 berm 1.5 <br />9 Remove all equipment from site 1.0 <br />10 Seed, mulch and place tree saplings in remaining <br />reclaimed azea 1.0 <br /> <br /> TOTAL 74S <br />Since We operation will only be active for 6 months per yeaz, the full gold mining operation will <br />take approximately 12-13 yeazs. <br />Alma Placer 7/03 <br />12 <br />