Laserfiche WebLink
enclosed sketch, will be installed to 20-feet and sealed at eight <br />Peet so it monitors Pluid level in the lower horizon of the coal <br />waste material. The other piezometer, shown as P-6 on the <br />enclosed sketch, :will be installed to 8-feet and sealed at two <br />feet so it monitors fluid level in the upper horizon of the coal <br />waste and in the cover material. <br />SCHBDULB <br />The best time to perform the bench repair work is during Septem- <br />ber and October. Delaying the work until late in the year will <br />allow the slump area to dry as much as possible. The delay will <br />also allow the seeding and mulching of the newly disturbed area <br />to be performed soon after the regrading work is completed. <br />Blue Ribbon proposes to perform the repair work in September and <br />October with the regrading work competed not later than the end <br />of October. Seeding and mulching of the area will be done in <br />late October or early November. <br />4 <br />