Laserfiche WebLink
<br />.Reclamation Bond Calculates <br />for <br />The Silver Syndicate Millsite <br /> <br />Assumption used in this calculation: Valuable machinery <br />equipment will be removed. Everything else - the mill b <br />ore stockpile, ope trenches, old machinery etc. may be <br />and tailings dispo 1 areas. The Millsite building and <br />also be contaminate with oils, leachates etc, which ne <br />than possible on the illsite. <br />1. <br />such as the milling <br />wild ng, tailings, an <br />1 t on the millsite <br />s grounding area may <br />d to be buried deeper <br />Estimate on a 40 X 40 ft building it would take people and a cat 1 day to <br />knock down the building a d burn up what can be urned. The rest needs. to be <br />trucked to a landfill (1 y for 2 men and the ton truck). <br />cost: Wage grade crew of 2 en @ $180/day $360.00 <br />Move on D-6 cat $336.00 <br />2 hrs cat work @ $51.7 hr. $103.54 <br />vehicle and mileage- 20 miles X .25 $50.00 <br />misc. supplies $25.00 <br />2. <br />Estimate a substantial pile of tali <br />disposal. <br />cost: Move on loader <br />Loader 8 hrs @ 34.70 hr. <br />truck 10-12 cy (3) 24hrs. <br />3 <br />and some ore could be left for <br />$273.00 <br />$277.60 <br />.91hr $1,053.00 <br />Need to dismantle above ground/portions \ f water line, cleanup area of trash, <br />old machinery etc. <br />cost: Wage grade crew @ $180 day <br />mileage, misc. suppli s (plastic bag etc.) $360.00 <br />$100.00 <br />lowboy with tractor h rs. @ 58.41 hr $350.46 <br />4. <br />Millsite Cost: D-6 cat $51.77/hr X 17 hrs $880.09 <br />Dispos of 740 cu. yds. of mater als: <br />L der 8hrs. @ 34.70 hr. $277.60 <br />t ucks 8hrs @ 43.91 hr. $351.28 <br />at 2hr. @ 51.77 hr $103.54 <br />Hau in 740 cu. yds new topsoil 4343.00 <br />@ 1.20 yd.to purchase and $4.68 yd. <br />to transport. <br />(1.67 acres dis urbed area approx. <br />,000 yds soil and subsoil to move) <br />