Lodestar Energy, Inc. <br />Munger Canyon Mine <br />Reclamation Estimate -Gob Pile <br />Assume worst case is when the covertill stockpile and topsoil piles are at capacity. <br />Topsoil Quantity 1,960 C.Y. <br />covertill Quantity 15,000 C.Y. <br />Dirt Work -Short Haul Distances <br />C.Y. Swell Unit Cost Total <br />1960 1.165 $ 1.50 $ 3,425 <br />15000 1.165 $ 1.50 $ 26,213 <br />Subtotal <br />Revegetation <br />Reclaim Sediment Pond <br />Sub-Total Estimated Cost <br />Burden Added on by DMG <br />$ 29,638 <br />Acres $/Acre <br />4.9 1000 $ 4,900 <br />$ 1,000 <br />$ 35,538 <br />25% $ 8,884 <br />Total Estimated Cost $ 44,422 <br />