My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
2007-08-10_REVISION - M2001107
DRMS
>
Day Forward
>
Revision
>
Minerals
>
M2001107
>
2007-08-10_REVISION - M2001107
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
6/15/2021 2:43:05 PM
Creation date
11/21/2007 9:36:31 AM
Metadata
Fields
Template:
DRMS Permit Index
Permit No
M2001107
IBM Index Class Name
Revision
Doc Date
8/10/2007
Doc Name
Application
From
Northern Colorado Constructors, Inc. Aggregate Div
To
DRMS
Type & Sequence
AM1
Media Type
D
Archive
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
184
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
EXHIBIT E <br />Reclamation Plan <br />Reclamation Limits <br />The mine will be reclaimed as a lined water storage reservoir with two interconnected cells. The <br />single reservoir cell that is in the current plan (approved in Technical Revision #3) will be <br />extended onto the southern portion of the amendment area tract. An additional reservoir cell will <br />be reclaimed in the northern portion of the amendment area tract. The two cells will be <br />interconnected via a pipeline so that the reservoir will function as one contiguous cell. The <br />configuration of the final reclaimed reservoir will be as shown in Exhibit F, Reclamation Plan <br />Map. <br />Methods and Criteria of Reclamation Activities <br />The current reclamation plan details the specific methods and criteria (topsoil handling, grading, <br />revegetation, seed mix, etc.) to be used in reclaiming the site. NCCI intends to continue to use <br />these methods. At this time a final liner design has not been completed. Until the final liner <br />design is completed NCCI commits to reclaiming the site with the clay liner approved in <br />Technical Revision #2 and commits to following the quality control plan approved in that <br />revision. This liner would satisfy the requirements of the "State Engineer's Guidelines for Lining <br />Criteria for Grave! Pits." <br />Reclamation Timing <br />Reclamation activities have not commenced to date on the site. As stated in Technical Revision <br />#3, NCCI is in active negotiations with a buyer for the reclaimed water storage reservoir site. <br />They are in the process of determining what the final liner configuration will be. When the final <br />liner configuration is determined, NCCI will start the reclamation and continue it concurrently <br />with the mining activities. <br />A phased and cumulative bonding approach has been approved in Technical Revision #3 to <br />ensure that NCCI has posted sufficient bond to reclaim the site at any point during the mining <br />activities. See Exhibit L, Reclamation Cost, for details of the phased reclamation costs that have <br />been updated to reflect the amended phasing and quantities. <br />M-2001-107 <br />NCCI PR #1 <br />ORMS 112 Permit Amendmenf <br />39 <br />
The URL can be used to link to this page
Your browser does not support the video tag.