Laserfiche WebLink
<br /> <br />INTEROFFICE <br />MEMORANDUM <br />TO: Joe Dudash <br />FROM: Jim Stark <br />SUBJECT: Bowie No. 1 Mine TR-33 Reclamation Cost Estimate <br />DATE: 21 August, 2000 <br />Attached is the reclamation cost estimate for Bowie No. 1 Mine's Technical Revision 33. <br />The estimate is two tasks (000 and 111) and represents an increase in liability of <br />$14,562.00. The increase in liability is due to the removal of the five new storage tanks <br />at the train loadout area. This amount is much higher that the $1,000.00 stated in the <br />cover letter of the application. I am not sure how this amount was calculated but it is not <br />correct. I agree with Jim Stover's statement [hat widening the haul road and not paving it <br />(increasing the disturbed area about 0.1 acres or 2000 CY) will not change the overall <br />liability for backfilling/grading the loadout azea. If you have any questions regarding this <br />estimate please let me know. <br />