January 15, 1996 <br />' Dozing <br />Estimate Track-type Tractor Productivity <br />Page 2 <br />del D8N Ident [GRD PONDS ] Hourly O&O [ 128.24] <br />Blade Type [ UNIV.] Dual Tilt [ 100] <br />Dozing Distance (feet) [ 100] Spoil Pile Factor [ 100] <br />Operator [ 75] Minutes Worked per Hour [ 45] <br />Grade [ 0] Bank Material Density [ 3,202] <br />Material Factor [ 100] Loose Material Density [ 2,545] <br />Dozing Factor [ 100] Coefficient of Traction [ 100] <br />Visibility [ 100] Direct Drive Transmission [ 100] <br />Altitude [ 100] Bank cu yds to Move [ 4,000] <br />Theoretical Production Under Ideal Conditions (Loose cu yd~h) 965 <br />Total Adjustment Factor 0.5104 <br />Adjusted Hourly Production Estimate (Sank cu yd~h) 392 <br />Adjusted Hourly Production Estimate {Loose cu yd/h) 493 <br />Operating Hours to Complete Job 10 <br />Equipment Expense to Move Required Volume $ 1,262 <br />Equipment Expense per Bank Cubic Yard $ 0.3205 <br /> <br /> <br />23-3-27 REVISED 01/30/96 <br />