<br />~~ <br />III IIIIIIIIIIIIIIII <br />REi`E r ~iF-;l <br />INSPECTION REPORT <br />JUL 0 8 1993 <br />Divisor, :r. ,~,:~~~,,.._ , <br />Site: National King Coal Mine, Hesperus, Colorado - /...,.~', <br />Inspected By: Don R. May, P.E., Project Engineer/~/ <br />Inspeotion Date: Quarterly Inspection, June 22, 1993 <br />June 29, 1993 <br />Coal Waste Pile: The coal waste pile and the surrounding area <br />were inspected for compliance with the state approved design and <br />for signs of instability and erosion. The base of the waste pile <br />area has been graded to form nearly level pad. It appears that a <br />fair amount of material has been laid down. This will form a good <br />base for the reshaping of the pile. Since the toe drain must be <br />at the intersection of the waste material and the natural ground, <br />they will have to excavate through this layer of waste to install <br />the drain. Lift heights and compaction appear adequate. See <br />photos. <br />Drainage Ditches/Pines: The Eastside Ditch which diverts upstream <br />flow around the mine is near completion. It has been roughed in <br />for the entire length. The bank slopes, in several places, are <br />steeper than 2:1. This may correct itself with time or they may <br />have to do more backhoe work. The channel has not been ripraped. <br />These conditions can be seen in the accompanying photos. <br />The 36" concrete yard drainage pipe is about 1/2 full of <br />sediment. Even though there is adequate flow capacity, even at <br />1/2 full, I recommend the construction of small sediment traps at <br />each inlet to this pipe. This will limit the sediment entering <br />the pipes which in turn will allow the clearer water to clean out <br />the existing sediment. <br />Sediment Ponds: The sediment ponds were inspected for excessive <br />sedimentation and erosion with no apparent problems. The pond <br />embankments are also in good condition. The elevation of the low <br />level outlet on the West Pond should be adjusted to comply with <br />the drainage plan. The pipe opening should be 1 ft. above the <br />pond bottom. In addition, the spillway crest on the West Pond <br />should be lowered to an elevation which provides 1 ft. of <br />freeboard, or 1.3 ft. below the crest. <br /> <br />