The schedule for construction of the check dams, Phase II, will begin <br />with dams being built in the uppermost portion of the watercourse and <br />continuing downstream. It is anticipated that the check dams will be <br />constructed at a rate of about three (3) structures per month. Using this <br />schedule, all twenty one (21) of the check dams will be completed over a <br />period of eight (8) work months. For the purposes of scheduling as iC <br />pertains to this hydrologic reconstruction plan, a work month consists of <br />twenty (20) work days having suitable weather and soil conditions for <br />excavation and construction activities. A work day is a calendar weekday. ~I <br />The schedule for construction of the terraces, Phase IIZ, will begin <br />with completing the remainder of Terrace 6. Since the watersheds above <br />this terrace will still be undergoing backfilling and final grading, it <br />will not be possible to construct any of the upslope terraces prior to this <br />time. Terrace 6 is designed to convey the runoff from all upslope terraces <br />and watershed areas, enabling this type of construction sequencing to be <br />performed. <br />After Terrace 6 has been constructed, the terraces downslope from <br />Terrace 6 will be constructed in a sequential manner. Since the grading of <br />the final pit along the western edge of West Ridge will not have been <br />completed prior to the construction of the terraces, all of the terraces <br />• downslope of Terrace 6 will be constructed beginning at the watercourse <br />between Center Ridge and West Ridge and progress westward along the slope. <br />The terraces will be constructed as far to the west as possible without <br />interfering with the final pit grading activities. Terrace 6 and those <br />portions of the downslope terraces discussed above will be completed within <br />seven working months following the check dam construction. <br />In Phase IV, the terraces upslope of Terrace 6 and the remaining <br />upper portions of the terraces downslope of Terrace 6 will be constructed. <br />Phase IV construction activities will be completed as soon as practical <br />after the final pit in the upper portion of West Ridge has been backfilled <br />and final graded. <br />From this schedule, it is estimated that a minimum of 15 work months <br />will be required to complete the West Ridge Hydrologic Restoration Plan. <br />Climatic conditions at the Edna Mine are generally favorable for working <br />with surface soils only four months during any given year (June, July, <br />August and September). Since the plan was implemented at the beginning of <br />the 1992 construction season, final completion of the reconstruction plan <br />• would be anticipated to occur by the end of the 1995 construction season. <br />7 <br />March 31,1994 <br />