My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
PERMFILE61052
DRMS
>
Back File Migration
>
Permit File
>
700000
>
PERMFILE61052
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
8/24/2016 11:07:45 PM
Creation date
11/20/2007 7:00:34 PM
Metadata
Fields
Template:
DRMS Permit Index
Permit No
M1979094HR
IBM Index Class Name
Permit File
Doc Date
5/21/1979
Doc Name
REGULAR 112 PERMIT APPLICATION FORM
Media Type
D
Archive
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
79
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
<br />D.5 Operation Timetable <br />• D. 5.1 Project Phases <br />Using the mine maps, Figures D.5-1 to D.5-11, in conjunction with Table <br />D-4, the areal extent and time schedule can be determined. Two phases <br />are involved with a transition between phase one and two occurring about <br />seven months into year four. (See Exhibit E.5, reclamation timetable <br />discussion.) <br />D.5.2 Mining & Reclamation Sequence <br />Year 1 <br />Removal of vegetation and topsoil will preceed waste dump establishment <br />in the valley area. Figure D.5-2 depicts the dump and pit configurations <br />at the end of the first year. A topsoil storage area will be established <br />and seeded for erosion control. Within the first year the road to JD- <br />• 7 underground facility will be relocated and the support buildings <br />constructed. Only overburden will have been removed from the pit at <br />this time. <br />Reclamation test plots will be initiated in the fall, located on the <br />western portion of the overburden and the topsoil stockpile. These test <br />plot areas will be topsoil-capped overburden and pit benches. The <br />establishment of general experimental parameters and the logistics of <br />the reclamation process will be first year objectives. <br />Year 2 <br />The spoil area has expanded after vegetation removal and topsoiling as <br />per Table E.5-1 and the second year mine map (Figure D.5-3). Some ore <br />bearing zones may be encountered with pit expansion but the primary <br />activity will still be overburden removal. <br />D-4 <br />