Laserfiche WebLink
• Timin <br />1 } Temporary pipe will be laid during sometime in 2001 and will be put into operation either <br />during for the latter part of the irrigation season of 2001 or will be ready for the 2002 season. <br />This will depend on mining advance. <br />2) After mining continues west of 2700 Road and the area for the permanent line has been <br />backfilled and graded, the permanent line can be installed and should be ready for the 2005 <br />irrigation season. <br />Temporary Relocation of BB Road <br />The mining of the amendment area will involve the ternporary relocation of portions of BB <br />Road. The timing of the relocation and the restoration is given in Table 2.05.3-10-3. The best <br />location for the main detour was north of the proposed operation and immediately south of <br />Tuttle Draw. Map <br />2.05.3-14 shows the detour road in plan view, which will provide access for all users north of <br />. the site along 2700 Road to and from Nucla. A special access turnout has been provided for the <br />Reeder and Garrett properties. Since the intersection of 2700 Road and BB Road (Sunshine <br />Ranch Corner) will also be removed, all existing users west on BB Road must be provided new <br />access. This is to be done by using the existing county road (BB 27) which goes west from <br />2700 Road approximately 1300 feet south of the Sunshine Ranch Corner and ends at the <br />Morgan house. An extension of this road will be provided to the Enstrom, Johnson and Wilcox <br />properties. These are the only users of the western portion of BB Road who will be affected by <br />the operation. BB Road ends at the W ilcox property. <br />The only traffic that will be slightly inconvenienced will be that traffic that travels from north of <br />the operation directly south on 2700 Road or in the opposite direction. This is a small <br />percentage of the traffic that uses the BB Road/2700 Road intersection. This traffic would have <br />to use the detour to go to the town of Nucla, approximately 1.0 miles further east. In some <br />cases, the destination of this traffic is somewhere south of Nucla, so there may actually be no <br />additional distance traveled. This detour is expected to be in effect from the time 2700 Road is <br />excavated in mid-2002 until mid-2004 when the road will be replaced with gravel. The following <br />year, the road would be paved in its original location. <br />. Main BB Road Detour Design Details <br />(REVISED ~Z00) Attachment 2.05.3(3) -10-125 <br />