• Horizontal Drainage: A horizontal drainage system will be required in the portion of the embankment <br />which is located on the down water side of the pond with an appropriate toe drain system. <br />The horizontal drainage system according to the Bureau of Reclamation Design of Small Dams should <br />be placed az shown in Figure 15. The blanket and toe drain should consist of a free draining granular <br />material with not more than 3% passing the number 200 sieve and a maximum particle size of 3 inches. <br />In addition, the drainage material should be wrapped with a fdter material such az M'trafi 140N or an <br />equivalent fabric approved by the soils engineer. The drainage blanket should be minimum of 3 feet <br />thick. <br />An alternate horizontal drainage system according to Muafi Fabric Filter design guidelines, would be <br />placed az shown in Figure 16. Using the "Design Guidelines for Subsurface Drainage Structures' by <br />Mirafi Fabric Filters, the drainage blanket should be a minimum of 1 foot thick. The granular material <br />may have 100% passing the 3/8" sieve, 70% passing the #8 sieve, 30% pazsing the #40 sieve and less <br />than 10% pazsing the #200 sieve for a permeability of 2 ft/day. The estimated permeability for Pond <br />005 is expected to be lower. <br />The toe drain should be placed az shown in Figure 15. The underdrain system should consist of a <br />series of 6-inch diarne[er, slotted P.V.C. pipes surrounded by a minimum of 6 inches of free draining <br />granular material. The granular material should extend up to the bottom of the next bench and should <br />contain less than 3% passing the number 200 sieve and more than 50% retained on the number 4 sieve. <br />The granular drainage materials should be wrapped wish a filter cloth such az Mirafi 140N or an <br />equivalent fabric approved by the soils engineer. <br />The drainage system along the pervious dam should extend across the natural channel to an <br />approximate elevation of 6872 feet or 45 feet perpendicular to the center line of the proposed dam, the <br />exact location will have to be determined in the field when the exact elevation of the channel is known. <br />An adequate layer of fill material should cover the drainage blanket in order to maintain its integrity. <br />Bazed on the site geometry the blanket drainage system will be approximately 250 feet in length <br />however, the actual dimensions should be determined in the field. <br />LIMITATIONS <br />This report has been prepared in accordance with generally accepted soil and foundation engineering <br />practices in this area for use by the client for design purposes. The conclusions and recommendations <br />submitted in this report are based upon the data obtained from the exploratory holes advanced at the <br />locations indicated on the plans. Ttte nature and extent o[ variations between the exploratory holes <br />may not become evident until excavation is performed. If during construction, soil, rock and <br />Job No. 91-562 Ground Engineering Consultants, Inc. Page 7 <br />