J <br />During geomembrane installation, the CQA Monitor shall observe and document deployment, trial <br />seams, field seaming, non-destructive and destructive seam testing, and repairs to assure that the <br />installation is in compliance with the SPECIFICATIONS. <br />Deployment -The CQA Monitor shall verify that only approved materials are used, each panel <br />is given a unique panel number, no geomembrane is placed during unsuitable weather <br />conditions as outlined in Section 02776, Article 1.05 of the SPECIFICATIONS, the <br />geomembrane is not damaged during installation, and anchoring is performed in compliance <br />with the SPECIFICATIONS and design DRAWINGS. The CQA Monitor shall record the <br />deployment on the deployment log form. <br />Trial Seams - The CQA Monitor shall verify that seaming conditions aze performed in <br />compliance with SPECIFICATIONS, tests aze performed at required intervals, specified test <br />procedures aze followed, and retests are performed in compliance with the <br />SPECIFICATIONS. If the ambient air temperature measured by the CQA Monitor is above <br />35°F for the entire day, the INSTALLER shall perform trial seams at the beginning of each <br />crew shift, and immediately following any work stoppage (i.e., for lunch, weather conditions, <br />etc.) of 30 minutes or more for each seaming appazams used that day. If the ambient av <br />temperature measured by the CQA Monitor is below 35°F for the entire day, the <br />INSTALLER shall perform four (4) trial seams, at approximately the same time interval <br />throughout the scheduled work day. Each Seamer shall make at least one trial seam each day. <br />Seaming operation shall not commence until the CQA Monitor has determined that the <br />seaming process is meeting the SPECIFICATION requirement and is acceptable. The CQA <br />Monitor shall record the trial weld results on the trial seam log form. <br />• <br />Field Seamine -The CQA Monitor shall verify that only approved equipment and personnel <br />perform welding, all welding is performed under suitable conditions as specified in the project <br />SPECIFICATIONS, specified overlaps aze achieved, seams aze oriented in compliance to <br />project requirements, and that grinding techniques and extrudate meet project requirements for <br />extrusion welding. The CQA Monitor shall record all field seaming on field seaming log <br />forms. <br />Non-Destructive Seam Continuitv Testine -The CQA Monitor shall verify that all seams and <br />repair aze non-destructively tested in compliance with the project SPECIFICATIONS. If a <br />seam cannot be tested, the CQA Monitor shall observe cap strip operations. The CQA <br />Monitor shall verify that test equipment and gauges aze functioning properly and that test <br />procedures aze in compliance with the project SPECIFICATIONS. The CQA Monitor shall <br />verify that all seams and repairs with failing test results aze repaired and/or re-tested until <br />passing results are achieved. The CQA Monitor shall record all non-destructive test locations <br />on the vacuum test and pressure test log forms. <br />Destructive Seam Testine -The INSTALLER shall obtain samples, at locations selected by <br />the CQA Monitor, of the field seamed geomembrane approximately 24 inches along and 12 <br />inches across the seam and centered over the seam as follows: <br />- a minimum of one sample per day; <br />- a minimum of one sample for each geomembrane seamer; <br />- a minimum of one sample every 500 feet of seaming; and <br />- seams that appeaz suspect to the CQA Monitor. <br />Section 01400.2 Page 7 of 1 I <br />Geosynthetic CQA Plan Golder Associates <br />I \00\2IOl\04W\CERTAEPo802lAPPENDSWPPE\014002RS.000 <br />Mazch 22, 2000 <br />Revision 5 <br />