Laserfiche WebLink
III. COMMENTS -COMPLIANCE <br />Below are comments on the inspection. The comments include discussion of observations made <br />during the inspection. Comments also describe any enforcement actions taken during the inspection <br />and the facts or evidence supporting the enforcement action. <br />gradient is met. The extent of disturbed azea slope draining into the diversion appears to exceed the %z acre <br />projected and modeled in the permit. Operator will need to implement additional sediment control <br />measures along the length of the ditch if permit specified soil roughening and mulching are not fully <br />effective in preventing excessive contribution of sediment into the ditch. <br />The upper segments of the CRDA-2 East Collection Ditch, that drain the benches currently being <br />reclaimed, will need to be graded to fmal design configuration andriprapped in accordance with permit <br />specifications in association with CRDA-2 fmal grading andtopsoiling. <br />Coal Creek Permanent Diversion <br />The Coal Creek permanent diversion appears to have been essentially completed, largely in compliance <br />with approved design. At one location near the lower end of the segment just above the 72" culverts, <br />additional grading appeazed to be warranted to better define the channel and ensure compliance with design <br />depth specification. In one other location further upstream, the channel is somewhat constricted by <br />sandstone outcrop, and may not meet channel width specification. However, in this location, channel depth <br />significantly exceeds specification, and channel capacity would appeaz to be adequate without <br />modification. Any such deviation from design spec will need to be addressed in theP.E. construction <br />certification, and the implications with respect to channel capacity and functioning assessed. <br />At the upper end of the channel segment immediately below the concrete dip section, the south bank of the <br />channel had been protected with a 300 foot section of large riprap. Due to the low frequency of significant <br />flows in the channel, the remaining channel banks should be seeded with thegreasewood components <br />permanent seedmix. Most of the channel slopes will require additional roughening bydozer tracking or <br />other methods to prepaze a suitable seedbed. Topsoil piles 7, 8, and 9, adjacent to the channel segment on <br />either end of Pond 10 had been used up during the CRDA-2 reclamation project. These disturbance areas <br />and additional miscellaneous disturbances along the lower flat areas adjacent to the channel will need to be <br />ripped, seeded and mulched, also with the greasewood components mix. Upon completion of all dirt-work, <br />operator will need to ensure that required small azea exemptionberms are intact, for those portions of the <br />stockpile disturbance that do not drain into Pond 10. <br />CRDA-1 <br />There was no activity at CRDA-1 at the time of inspection. Grading on the pile has resulted in a slightly <br />crowned top of pile, per approved design. Reconstructed Terrace Drain #4 has been roughly established, <br />and the over-steepened crest noted in previous inspection reports had been eliminated, with the exception <br />of a short segment of the terrace drain at the northwest end. Additional work will be required to establish <br />final terrace grade, and to achieve design grade on the refuse slope above the terrace, in some locations. <br />A section of the inside ditch along the "in pit" road above the forks of Haul Road 5 and the XCEL ash road <br />had been partly obscured by construction traffic crossing over onto [he terrace bench. The ditch needs to be <br />re-defined, and a temporary culvert segment installed. Upon completion of the project, the ditch segment <br />and water bars along the "in pit" road segment will need to be reestablished. <br />