General Mine Plan Compliance <br />The timetable and schedule for completing reclamation is set forth on page 5-33 of the permit application, <br />as follows: <br />"Reclamation of the Carbon Junction Mine is slated to begin in the autumn of 2002 and continue through <br />completion. The completion of the tasks identified and described above [i.e. most reclamation tasks - TKJ <br />is anticipated to take three construction seasons (through summer of 2005). With completion of the <br />earthmoving and retopsoiling, seeding and planting is contemplated in the autumn of 2005. Should this <br />timetable need to be altered, OEI will apprise CDMG and revise the permit." <br />The last significant amount of reclamation activity in the permit azea was in 2003 when the South pit area <br />was reclaimed. <br />