III. COMMENTS -COMPLIANCE <br />Below are comments on the inspection. The comments include discussion of observations <br />made during the inspection. Comments also describe any enforcement actions taken during <br />the inspection and the facts or evidence supporting the enforcement action. <br />Flatiron Companies submitted a Phase II and III bond release application last summer. It was <br />deemed complete on September 9, 1999. This inspection was a complete inspection to <br />evaluate whether the Phase II and Phase III, final bond release criteria have been achieved. <br />Participating in the inspection were: Scott Patten representing Flatiron Companies; Randy <br />Pair representing OSM and myself representing DMG. The weather was cloudy with <br />intermittent light rain. <br />Records <br />A copy of the final bond release application was on file at the Jackson County Courthouse. <br />Sians and Markers <br />The entrance sign continues to be posted at the west entrance. <br />Roads <br />There are two roads on the Bourg Mine, the perimeter road and the oil company road. Both <br />have been approved as permanent roads. The perimeter road is rough, but very functional <br />for access purposes. Nielson & Associates, the landowners, built the road traversing the mine <br />site to gain access to a well they own east of the mine. The road has been well maintained <br />with good drainage off the road. <br />Jackson County added the entrance road to the county road system in 1988. One culvert <br />exists under the county road at the west entrance gate. The road is maintained by the <br />county. <br />Hydroloaic Balance <br />During the final reclamation, Flatiron Companies applied for received approval to create an <br />alternative sediment control system. The ponds were removed and a series of terraces were <br />constructed to control runoff off the reclaimed mine. This system has functioned very well at <br />the Bourg Mine. No evidence of rill, gullies or off-site sediment deposition was observed. <br />Following approval of the alternative sediment control system, the surface water monitoring <br />program was discontinued. Surface water quality was monitored through annual rill and gully <br />inspections and vegetative cover monitoring. Some rills and gullies were observed for the first <br />couple years after the installation of the terraces, but for approximately the past five years, <br />there has been no additional rills or gullies. Vegetative cover is very good and there has been <br />no reported surface water flow at the mine site. <br />During operations there were four sediment ponds. The reclaimed pond sites were inspected. <br />There are slight depressions in the pond areas, particularly Pond C and H, but they are well <br />vegetated and they do not hold water. The ground in the Pond C site was damp last spring, <br />but the area was dry in July. <br />A permanent gully was approved in 1990. The reclaimed gully is located just east of the <br />entrance and flows north to Mann Draw. The gully now blends in well with the surrounding <br />reclaimed lands and is well vegetated. No problems have been noted with the gully for <br />several years and none were observed during this inspection. <br />Two alluvial monitoring wells remain on site, Well 30A and 33C. They are located in Mann <br />Draw. Biannual data has been collected by Flatirons since 1989. To date, there have been <br />