Laserfiche WebLink
INSPECTION REPORT - PAGE 2 <br />FILE N0. <br />DATE: October 23, 1984 <br />OBSERVATIONS OF IMPORTANCE: <br />1. Construction of the Middle Fork diversion structure in the retort area <br />is proceeding towards completion. At this point in time, it is <br />approximately 60X complete. The operator anticipates completion this <br />construction season. <br />2. Construction of the lower Davis Gulch diversion structure within the <br />confluence area is also underway. Work on the Davis Gulch diversion <br />channel is approximately 40% complete. <br />3. Excavation of the "excess fill" and backfilling of the crusher <br />excavation in the mine bench is approximately 70% complete. The <br />operator anticipates completion of this project within the next month. <br />4. Construction of the Middle Fork Dam is complete. The quarry associated <br />with the Middle Fork Dam has been built, but not topsoiled or seeded. <br />Final grading is being completed in areas adjoining the dam. <br />5. The project lower sediment ponds have been cleaned of sediment. <br />6. Snowfall prevented access to the plant site during the inspection, as <br />well as the upper waste pile areas within Davis Gulch. <br />7. The Colorado River diversion site was inspected and found to be in <br />compliance. <br />RECOMMENDATIONS: <br />JAP/mad <br />Doc. No. 5012E <br />