Pad work is complete, and the cuttings pit has been excavated and lined to accommodate 18-Right Ventilation <br />Shaft mine development waste. See picture above. <br />Coal was being hauled out by truck and train (two train loadouts were observed during this inspection). <br />FISH AND WILDLIFE <br />The current condition of raptor protection devices could not be determined for some portions of some electric <br />lines that were inaccessible due to snow conditions. The periodic re-inspection of these lines will be <br />completed upon return of conditions that permit access to the sites. <br />REV EGETATION <br />As for backfilling grading, most areas of disturbance are of long-term mining and reclamation activities. <br />Those areas that have been backfilled, graded, and seeded as part of the design and construction of the feature <br />(such as buried utility lines) were covered with snow. <br />SUBSIDENCE <br />The lit Half 2004 Subsidence Report has been amended appropriately. Areas of active subsidence were not <br />accessible due to deep snow cover. <br />EXCESS SPOIL & DEVELOPMENT WASTE <br />Shaft development has not been started, and no development waste cuttings have been placed in the lined pit <br />at the 18-Right Ventilation Shaft site to date. <br />RECLAMATION SUCCESS <br />As indicated above, surface disturbances at the Foidel Creek Mine Site aze in azeas of long-term mining <br />features. There has been no discrete reclamation work accomplished, and there has been no reclamation bond <br />release request for any portion of the permit. There has been some reclamation of disturbed area work, such as <br />backfill, grading and seeding over buried utility lines. Such areas were covered with snow at the time of this <br />inspection. <br />C-1982-056. CC Inspection of January 4, 2005, Page 5 of 6 pages. BGW <br />