<br />P:\Projects\0106.069 CC&V 2024 CQA\J-REPORTS\2024 Phase 3B Subgrade and Leak Detection ROC Report <br /> Page 11 <br /> <br />4. PROJECT DEVIATIONS <br />Throughout construction, the following deviations from the IFC drawings and Specifications were <br />made and were approved by the Project Certifying Engineer. <br /> HDPE single sided textured geomembrane was placed as the geomembrane in the leak <br />detection trenches. NewFields notified CC&V of the substitution allowance by letter. The <br />letter explaining the reasoning for allowing the substitution is presented in Appendix J. <br />The letter was reviewed by the Colorado Division of Reclamation, Mining and Safety in <br />August of 2024. <br /> The final slope above the lined pad in isolated areas was finished to steeper than <br />envisioned on the IFC drawings, however the perimeter bench was widened to maintain <br />the overall slope of 2(H):1(V). <br />5. ENGINEER’S OPINION <br />Based on the construction activities observed, testing performed, and inspections completed, <br />NewFields certifies that the project was constructed in general accordance with the approved <br />design and technical specifications. <br />Sincerely, <br />NewFields, <br /> <br /> <br />Tyler Wendlandt <br />Project Resident <br /> <br />Jay N. Janney-Moore, PE <br />Project Certifying Engineer