<br />COST SUMMARY WORK
<br />
<br />Task description: Colowyo Renewal No. 8
<br />Site: Colowyo Coal Mine Permit Action: RN8 Permit/Job#: C1981019
<br />
<br />PROJECT IDENTIFICATION
<br />Task #: 000 State: Colorado Abbreviation: None
<br />Date: 8/16/2022 County: Moffat Filename: C019-000
<br />User: ZTT
<br />Agency or organization name: DRMS
<br />
<br />TASK LIST (DIRECT COSTS)
<br />Task
<br />Description
<br />Form
<br />Used
<br />Fleet
<br />Size
<br />Task
<br />Hours
<br />
<br />Cost
<br />001 Drill and Shoot South Taylor Highwall - Cast Blast
<br />(3000 ft)
<br />BLASTING 1 879.14 $1,381,065
<br />002 Load and Haul Spoil to TS-1 TRUCK1 1 1,078.51 $5,181,656
<br />003 Load and Haul Spoil to TS-2 TRUCK1 1 556.59 $2,417,287
<br />004 Load and Haul Spoil to TS-3 TRUCK1 1 310.99 $1,350,658
<br />005 Load and Haul Spoil to TS-4 TRUCK1 1 449.83 $1,746,068
<br />006 Load and Haul Spoil to TS-5 TRUCK1 1 134.66 $522,698
<br />007 Load and Haul Spoil to TS-6 TRUCK1 1 383.90 $1,490,152
<br />008 Load and Haul Spoil to TS-7 TRUCK1 1 753.43 $3,272,183
<br />009 Load and Haul Spoil to TS-8 TRUCK1 1 1,513.25 $6,572,099
<br />010 Load and Haul Spoil to TS-9 TRUCK1 1 1,298.12 $6,236,735
<br />011 Load and Haul Spoil to TS-10 TRUCK1 1 1,329.69 $6,388,428
<br />012 Load and Haul Spoil to TS-11 TRUCK1 1 1,148.55 $5,518,139
<br />013 Load and Haul Spoil to TS-12 TRUCK1 1 1,186.67 $5,153,773
<br />014 Load and Haul Spoil to TS-13 TRUCK1 1 1,173.66 $5,097,263
<br />015 Load and Haul Spoil to TS-14 TRUCK1 1 1,343.44 $5,834,627
<br />016 Load and Haul Spoil to TS-15 TRUCK1 1 1,295.19 $6,222,686
<br />017 Load and Haul Spoil to TS-16 TRUCK1 1 408.17 $1,772,716
<br />018 Load and Haul Spoil to TS-17 TRUCK1 1 408.17 $1,772,716
<br />019 Load and Haul Spoil to TS-18 TRUCK1 1 228.26 $886,013
<br />020 Load and Haul Spoil to TS-19 TRUCK1 1 71.35 $276,943
<br />021 Load and Haul Spoil to TS-20 TRUCK1 1 133.62 $580,338
<br />022 Load and Haul Spoil to TS-21 TRUCK1 1 197.26 $765,687
<br />023 Load and Haul Spoil to TS-22 TRUCK1 1 102.38 $397,419
<br />024 Regrade Gossard Loadout DOZER 4 2.36 $5,712
<br />025 Rip Facilities Area RIPPER 4 60.17 $149,718
<br />026 Rip Coal Stockpile Area RIPPER 4 10.36 $25,784
<br />027 Rip Gossard Loadout RIPPER 4 0.96 $2,401
<br />028 Rip Haul Road A and Haul Road B RIPPER 4 3.14 $7,830
<br />029 Regrade Haul Road A Upper and Lower Ditch DOZER 1 0.32 $184
<br />030 Rip Gossard Loadout Road RIPPER 4 1.26 $3,139
<br />031 Regrade Gossard Loadout Road DOZER 4 1.70 $4,130
<br />033 Reseed Road to Power Pole REVEGE 1 0.80 $232
<br />034 "Mine" Riprap from South Taylor Pit Temporary
<br />Stockpiles for
<br />SITEMAINT
<br />ENANCE
<br />1 0.00 $1,249,424
<br />035 Regrade Prospect Pond DOZER 1 34.19 $11,907
<br />036 Regrade Streeter Pond DOZER 1 77.75 $27,075
<br />037 Regrade Gossard Loop Pond DOZER 1 2.28 $795
<br />038 Regrade Rail Loop Pond DOZER 1 0.99 $345
|