EXHIBIT E- RECLAMATION PLAN <br /> This information provided in this Exhibit is intended to satisfy the requirements outlined in Section <br /> 6.4.5 of the Colorado Mined Land Reclamation Board Construction Material Rules and <br /> Regulations: The proposed mining and reclamation plan focuses on minimizing the ecological <br /> impacts of mining, minimizing the length of time of impact, and maximizing long-term benefits. <br /> North Cell—mined in year one and reclaimed concurrent with mining South Cell. <br /> South Cell—mined in year two through four and reclaimed concurrently. <br /> (a) A description of the type(s) of reclamation the Operator proposes to achieve in the <br /> reclamation of the affected land, why each was chosen, the amount of acreage <br /> accorded to each, and a general discussion of methods of reclamation as related to <br /> the mechanics of earthmoving; <br /> The mined area will be reclaimed to 4-feet below existing grade and tie into existing grade <br /> on the perimeter of the mine. The mine will include a 20-foot buffer around the perimeter <br /> of the excavation. <br /> The North Cell will be excavated at a 3 to 1 horizontal to vertical slope and will be <br /> backfilled back to native grade with overburden or sand from the South Pit. <br /> The South Cell will be excavated down at a 3 tol horizontal to vertical slope on the <br /> southwest side, along with feathering grades back into existing on the east by Weld <br /> County Road 29. <br /> All excavation will be amended and planted with crops or dryland native grasses. Historic <br /> drainage patterns will be maintained. Refer to Exhibit F for the acreages and additional <br /> details. <br /> Earthmoving <br /> The soil amendment will be placed by a loader and generally graded with a blade. All <br /> grading will be done in a manner that controls erosion and siltation of the affected lands, to <br /> protect areas outside of the affected land from slides and other damage. In addition, all <br /> backfilling and grading will be completed as soon as feasible after the mining process. All <br /> disturbed areas will be regraded and smoothed to a finished grade that is suitable for <br /> revegetation of the final land use. See attached mining plan for historic and proposed <br /> grades. <br /> As noted previously, the area will be reclaimed as mining commences. Finish grading, <br /> topsoil/soil amendment placement and seeding will occur once the resource is completely <br /> removed per phase. <br /> (b) A comparison of the proposed post-mining land use to other land uses in the <br /> vicinity and to adopted state and local land use plans and programs. <br /> Once the site is reclaimed it can returned to being farmed. <br /> David Hunt—Strear Dirt Mine—MLRB 112 Permit Amendment Application <br /> Exhibit E-1 <br />