Laserfiche WebLink
4. Reclamation Timetable and Sequence <br /> The sequence and timing of reclamation can be seen in Table E-4 below. The reclamation <br /> schedule is dependent on the rate of mining and fluctuating market demands. The operator will <br /> reclaim the site concurrently with the progression of mining to limit the total disturbance. <br /> Table E-4 Reclamation Timetable <br /> Description Tune Required <br /> Develop and mine Northern Phase 3 years <br /> Develop and mine Southern Phase 3 years <br /> Backfill,topsoil,and revegetate remaining 1 year <br /> disturbances <br /> Vegetation monitoring 2 years <br /> Total 9 years <br /> 5. Revegetation Plans <br /> Seed will be placed in all areas to be vegetated following grading, topsoiling, and discing of the <br /> soil. All disturbances that are retopsoiled will be seeded with a Rangeland Seed Mix. The Weld <br /> County recommended mix to be used is as follows: <br /> 5.1. Rangeland Seed Mix <br /> Species Pounds of pure live seed <br /> per acre(drilled) <br /> Sand Bluestem 1.0 <br /> Sand Lovegrass 2.5 <br /> Indian Ricegrass 3.0 <br /> Prairie Sandreed 0.75 <br /> Green Needlegrass 1.5 <br /> Little Bluestem 0.75 <br /> Yellow Indiangrass 0.5 <br /> Switchgrass 1.5 <br /> Sand Dropseed 0.5 <br /> Total 12.0 <br /> Broadcast seeding will be done at double the drill rate. Mulch will be placed at roughly 4000 <br /> pounds per acre. <br /> Marcovich Gravel Pit <br /> May 2024 E-3 U Lewicki&Associates <br />