AR4 <br />Please update the provided Mining Plan and Mining Plan map for TR9 <br />to include/show the following items at a minimum: <br />a. Location(s) and volume(s) of the proposed approx. 1.3 Mcy of <br />material that will need to be mined as backfill material for the Satellite <br />South Pit. How will the mining plan be modified and monitored to <br />insure that this material remains on-site for use as backfill? <br />As has been discussed in virtual meetings with DRMS in November and December <br />2023, and summarized in Section 2.1 of the TR, this TR focused on modifications <br />to the mining and reclamation plans to support continued operations at the <br />Morrison Quarry while the application for a plan for augmentation is under court <br />review. Assuming the augmentation plan is approved, Holcim-WCR, Inc. intends <br />to further develop the South Quarry below elevations approved in AM07, as <br />modified by this TR09, referred to as Phase IV on the mining plan. This Phase will <br />be addressed in a future amendment. <br />As is discussed in Section 2.3 of the TR09 document, Schedule for Satellite South <br />Pit Buildout , the satellite pit will take approximately three years to complete. <br />Over the next three years, mining will progress concurrently in the West Quarry <br />and Satellite South Pit. In early 2027, the current mine plan has the West Quarry <br />mining advancing to El. 6944 bench. The current reserve analysis for the South <br />Quarry, below the West Quarry, from El. 6944 to El. 6600 is 11 million tons of <br />mineable gneiss and 2.5 millions tons of waste material (the volume needed to <br />backfill the satellite south pit). In the event that the Augmentation Plan is not <br />approved, Holcim intends to continue mining the South Quarry (below the West <br />Quarry El. 6944 bench) in accordance with the approved mining plan and using <br />material from this area to backfill the satellite south pit. <br />Exhibit E - Reclamation Plan has been updated to reflect this change in strategy. <br />No changes have been made to Exhibit D - Mining Plan. <br />Exhibit D-1 and D-1b: Mining Maps - have been updated to include a text box <br />noting the location of reserves for backfill. <br />Exhibit D-1 and Exhibit D-1b Mining <br />Maps. P. 6, 8. <br />Exhibit E - Reclamation Plan. p. 10- <br />12. <br />AR5 <br />Please update the provided Mining Plan and Mining Plan map for TR9 <br />to include/show the following items at a minimum: <br />b. Location and volumes of the proposed approx. 1.3 Mcy of existing <br />on-site material that will be stored on site for use as backfill for the <br />Satellite South Pit. <br />As discussed in the response to AR4, the reclamation strategy has been modified <br />to remove the use of existing on-site stockpiled material. All material needed for <br />the backfill will be generated on-site in permitted areas of the quarry in <br />accordance with the approved mining plan. <br />No updates to the Mining Plan or Mining Plan map have been completed. <br />Exhibit E - Reclamation Plan. P. 10- <br />12. <br />1