2. Topsoil Replacement <br /> Topsoil will be replaced in a single 2-inch lift across all disturbed areas at the Anderson Pit. It will be <br /> directly placed via loaders and haul trucks. This will follow the regrading and backfilling of slopes <br /> and will be part of the concurrent reclamation. All areas will be disced following the topsoil <br /> replacement to aid in root penetration. <br /> 3. Site Access <br /> The site access will remain in place after reclamation for use by the landowner. No reclamation <br /> work is required for the access road. <br /> 4. Reclamation Timetable <br /> The sequence and timing of reclamation activity can be seen in Error! Reference source not <br /> found. below. This schedule is dependent on the rate of mining, which will fluctuate with market <br /> demands. The operator will reclaim areas of the site as mining moves on to ensure limited <br /> disturbance. Some areas of the site have already been partially reclaimed. <br /> Table E-1 — Reclamation Timetable <br /> Description Time Required <br /> Develop and mine remaining mining areas, reclaiming concurrently. 18 years <br /> Backfill, topsoil, and revegetate remainder of the site that is 1 year <br /> unreclaimed <br /> Vegetation monitoring 2 years <br /> Total 21 years <br /> Anderson Pit <br /> September 2023 E'2 Lewicki&Associates <br />