Laserfiche WebLink
<br /> <br />1.4 DETERMINATION OF BOND <br /> <br />Trapper Mining Inc. presently maintains a reclamation performance bond for the Trapper <br />Mine payable to the State of Colorado and the United States Office of Surface Mining <br />Reclamation and Enforcement. Upon approval of this permit application, a performance <br />bond or equivalent, acceptable surety will be secured in an amount equal to the estimated <br />costs for returning the affected area to a satisfactory condition as defined by applicable <br />regulations and this permit application. <br /> <br />The equipment productivity estimates used in regrade time calculations were derived from <br />the Caterpillar Performance Handbook, edition 49. Topsoil fleet hours were derived <br />using TALPAC haulage simulation software. DRMS database ownership and operating <br />costs were used where available; otherwise, these costs were extracted from Trapper <br />Mining Inc. historical data and information obtained from Wagner Equipment Rentals. <br /> <br />All reclamation costs were calculated according to the worst-case condition of reclamation <br />requirements. The costs that were calculated in this manner realistically represent those the <br />Division could incur at any time during the permit period, and not just for the conditions that <br />may exist at the end of the five years. Appendix A Tables A-1 through A-14 summarize <br />regrade, topsoil replacement, revegetation areas & costs, demolition, and miscellaneous <br />costs associated with mine closure. The driving factor in determining the worst-case year <br />was the extent to which Ithaca (I), Jennings (J), Colt (C), Lancaster (L), and Nighthawk (N)- <br />pits have been opened. <br /> <br />During the proposed worst-case year, which is estimated to be 2023, the depth and resulting <br />volume of material required to backfill C, I, J, N, and L pits is at its maximum, with respect to <br />the permit term. The projected new disturbance, which includes the dragline, dozer <br />stripping, and truck/Excavator operations, is greatest in the year 2023 (see Table 1.4-2). <br /> <br />The primary contributing factor to the increase in the projected Performance Bond for the <br />worst-case bond year of 2023 is the development of C, I, and J Pits. These pits will be <br />opened in 2022, with topsoil stripping operations and development of the initial box cuts. <br /> <br />By 2023, N pit will have advanced to the point that much of the box-cut is open, with some <br />additional pre-stripping having occurred, thus resulting in a substantial area of pit being <br />open. In addition, highwall mining in the initial boxcut is in progress, which will require a <br />delay in reclamation activity during this process. <br /> <br />The Ash Pit is anticipated to still be receiving ash from Craig Station. There will be some <br />reclamation done in the ash pit by 2023, but a significant portion of the pit will remain open <br />beyond the permit term. <br /> <br />Derringer/Enfield Pit, previously anticipated to receive ash, will be partially graded in 2022, <br />but will not be Phase I bond released, and therefore will be included back into the PR11 <br />Bond Estimate. <br /> <br />As L pit advances eastward, the cuts tie into the former East A (AE) pit. AE pit has been <br />incorporated into L pit and, therefore, will be no longer be referred to as a separate pit. <br /> <br />Due to the pre-stripping operations with the Truck/Excavator fleet, combined with the dozer <br />stripping and dragline operations, L pit’s overall disturbance area, with respect to the five <br />year permit term, is greatest in 2023 (see Table 1.4-2 ). <br /> <br />1-31