Wattenberg Lakes Amendment, Exhibit E—Reclamation Plan May 2023 <br /> EXHIBIT E - RECLAMATION PLAN <br /> 1.0 GENERAL <br /> Area 1 and Area 2 will be mined and reclaimed as part of the development of Pond 1 (Struck Pond)that the <br /> landowner, the City of Westminster,will own and use for water storage. Pond 3, previously reclaimed through <br /> construction of the slurry wall,will also be used by the City of Westminster for water storage; please see <br /> Technical Revision JR) 1 for slurry wall technical specifications and construction completion report(12/18/2014), <br /> approved by DMRS (1/8/2015). Other un-reclaimed but previously mined areas within the permit boundary will <br /> also be reclaimed through backfilling, as needed, and minor grading, and establishment of plantings and ground <br /> covers to restore and enhance all areas disturbed by current or previous mining activities. <br /> The primary changes in the current DRMS permit amendment reclamation plan compared with the 2004 DRMS <br /> permit reclamation plan include the following (changes to the mining plan are noted in Exhibit D): <br /> • Pond 1, now called the Struck Pond, has an expanded footprint to the west of the originally planned pond <br /> in the area previously identified for wetland mitigation area and slightly north as well; this adjustment to <br /> the north results in an addition to the affected area covered under the 2004 permit, thus requiring this <br /> amendment. <br /> • Pond 2, identified in 2004 in the west-northwest part of the permit area, now is planned for wetland <br /> mitigation with part of the area to remain dedicated for access to two remaining producing oil wells. <br /> • The Pond 3 boundary along the west side was straightened during mining and a slurry wall was <br /> constructed around the revised pond perimeter. <br /> • Some of the previously identified wetland mitigation areas are changed in location to accommodate <br /> revised plans for future use of the site. <br /> • The wetland planting list is updated based on recent information including a wetland survey. <br /> Key considerations for preparing this reclamation plan include the following: <br /> • All wetlands on the site were located and delineated in June and August 2022. Existing wetlands will be <br /> avoided to the extent feasible during mining, earthmoving, and reclamation activities.Also,wetlands will <br /> be created in the identified wetland mitigation areas. <br /> • Maintenance activities on the site will also include a comprehensive Weed Management Plan to limit the <br /> spread of invasive species into the riparian areas and wetlands. <br /> • The Pond 1 (Struck Pond) reservoir will be isolated from the surrounding alluvial aquifer by constructing a <br /> slurry wall; a perimeter drain will also be constructed to minimize impacts of the slurry wall on <br /> groundwater flow through this area. <br /> • Multiple groundwater monitoring wells are located within the permit area and will continue to be <br /> monitored before, during, and after the mining and reclamation are completed. The wells will be used to <br /> monitor effects from mining and provide information for mitigation of potential impacts on groundwater <br /> levels and riparian vegetation, as necessary. See Exhibit G for more information. <br /> 2.0 RECLAMATION OVERVIEW <br /> As discussed in the Mining Plan (Exhibit D), Holcim anticipates conducting operations under this DRMS permit <br /> amendment in three phases for a total duration of 18 months,with mining of Area 1 and Area 2 planned for only 2 <br /> months of that duration (in Phase 1 only). The reclamation activities in these three phases will occur concurrently <br /> (for Phase 1)or within nine months after completion of Phase 1 (for Phases 2 and 3). Reclamation will focus on <br /> constructing the pond liner/slurry wall and also general backfilling and earthwork leading up to planting and <br /> seeding to establish vegetation in the disturbed areas. Reclamation, including regrading and seeding, will be <br /> completed within 2 to 5 years following initiation of these remaining reclamation activities. The three phases are: <br /> 1. Phase 1 —Concurrent activities (10 months) <br /> a. Grade/fill to achieve side slopes of 3:1 <br /> OTETRA TECH P a g e 1 1 6 <br />