Coal Basin Slope Stabilization Project <br /> 23rd Construction Grant <br /> I. PROJECT OVERVIEW <br /> The purpose of the Coal Basin Slope Stabilization Project was to minimize sediment transport <br /> from four mine bench outslopes by manipulating overland flow characteristics, revegetating the <br /> slopes, and planting shrubs at the base of each slope. The project was funded by a Colorado <br /> non-point source grant, the revoked bond and the U.S. Forest Service. <br /> II. LANDOWNER CONSENT <br /> The project was conducted on property managed by the United States Forest Service. This <br /> property was included within the permit area for the Coal Basin Mines, and therefore, no consent <br /> was required. <br /> Ill CONSTRUCTION <br /> PKA-5-545, Coal Basin Slope Stabilization Project <br /> Contract Number: C188369 <br /> Advertisement for Bid Dates: July 6, 2004 <br /> Pre-Bid Meeting Date: July 29, 2004 <br /> Bid Opening Date: August 11, 2004 <br /> Low Bid Amount: $373,193.00 <br /> Number of Bids: 1 <br /> Notice of Award Date: August 30, 2004 <br /> Notice to Proceed Date: September 20, 2004 <br /> Construction Start Date: September 27, 2004 <br /> Construction Completion Date: October 19, 2004 <br /> Final Settlement Advertisement Dates: <br /> Final Settlement Date: <br /> Contractor: Bitterroot Restoration <br /> Address: 445 Quast Lane, Corvallis Montana, 59828 <br /> Phone: 406-961-4991 <br /> Subcontractor: Western States Reclamation, High Country <br /> Equipment <br /> Final Cost: $241,159.20 <br /> Change Order(s): 1 (adds $10,355.20, 2 days) <br /> Feature Closure Summary <br /> No Features were closed during this project <br />