Sherman Mine Regrading Project <br /> Kessler Reclamation was the low bidder on the regrading project, which simplified the transition <br /> between projects. The completion of the demolition project and start of the regrading project <br /> overlapped each other by approximately one week. <br /> The regrading project encountered a variety of surprises and challenges, including a large <br /> quantity of trash which had been buried on site, an extensive wooden trestle which had been <br /> covered in mine waste, rock outcrops and an area of frozen mine waste. One change order to <br /> the regrading project was issued which addressed construction of a channel across the <br /> regraded mine waste to conduct the water flowing out of the ventilation portal. This water flow <br /> was not apparent during the initial investigation, or during the 2007 construction season. Not <br /> until the blowout occurred in July did this water become an issue. Conducting approximately <br /> 400 gallons per minute across the reclaimed mine waste required construction of a ditch <br /> approximately 4 feet wide across the bottom and 10 feet wide across the top, and approximately <br /> 500 feet long. <br /> During the regrading project, the Colorado Youth Corps came to the site for a week to assist in <br /> trash collection and removal of the upper portion of the retaining wall. Their work was greatly <br /> appreciated. <br /> Kessler Reclamation's flexibility in handling the unforeseen conditions contributed to the orderly <br /> flow of the project, as well as its timely completion. <br /> V. Feature Closure Summary— See Table. <br /> M:\imp\Costs FeatureClosures\Sherman Mine Reclamation FeatCloseSummary.xls <br /> M:\imp\Costs FeatureClosures\Sherman Mine Regrading Cost FeatCloseSummary.xls <br /> VI. FUTURE MAINTENANCE RECOMMENDATIONS <br /> The blow out of the ice plug in the ventilation portal demonstrates a serious potential problem. If <br /> the ice plug forms again, the resultant blow out will likely damage the site. A solid door was <br /> installed on a 60 inch corrugated metal pipe (culvert) which was backfilled, in and effort to <br /> prevent freeze up in the future. The ventilation portal should be monitored for conditions leading <br /> to freeze up of the portal, and if they appear to be occurring, an upper portal can be blocked off <br /> to reduce the amount of air allowed to flow through the mine. <br /> After the revegetation has stabilized, the site should be re-assessed to determine if shrub <br /> planting should be undertaken. One potential source of revegetation efforts would be the local <br /> Colorado Mountain College Natural Resource Management Program acting in cooperation with <br /> the Bureau of Land Management. They could conduct additional revegetation efforts and <br /> annual vegetation monitoring of the Sherman Mine Project area. In addition, periodic DRMS <br /> inspections will be made to ensure the integrity of the closures remain intact. <br />