EXHIBIT D <br /> Mine Phasing <br /> Mining will be completed in four main phases, one for each quarter-section of the property. The first <br /> phase will be the northeast quarter and future phases will proceed in a counter clockwise sequence. <br /> The overall time anticipated to complete all mining is 4 to 6 years,with each phase estimated to be <br /> completed in 12 to 18 months. The maximum area to be mined at any one time will be approximately <br /> 32.8 acres. <br /> BASELINE Korwell Land Holdings, LLC <br /> Korwell Soils Mine <br /> Engirwirg Planning Surveying DRMS 112 Permit Application <br /> 2 <br />