Colorado Inactive Mine Reclamation Program <br /> CLOSEOUT REPORT <br /> J and S Farms Bond Forfeiture Project(M-1996-053) <br /> Introduction: <br /> Permit Information <br /> DRMS Permit Nos. Operator Name Mine Names <br /> (M-1996-053) <br /> Carder Inc. J and S Farms <br /> Type of Mine -Gravel Commodity Mined- Aggregate <br /> Pre-Reclamation Site Conditions <br /> The J&S Farms Pit (M-1996-053) is in western Prowers County approximately 1450 feet north of the Arkansas <br /> River on the east side of Highway 50 in the town of Lamar. Access to the site is from 7350 Highway 50, at the <br /> office of Semco Electric Motors. <br /> The J&S Farms site encompasses approximately 80 acres of rangeland that was disturbed during a gravel mining <br /> operation. Approximately 28 acres of the site is a groundwater exposed pond.The shoreline of the ponds was eroded <br /> creating almost vertical highwalls around the southern and eastern shoreline of the ponds. The reclamation work <br /> involved: 1)grading the southern and southeastern shoreline of the pond to a 3H:1V slope,2)seeding approximately <br /> 8 acres with a custom seed mix. <br /> Bidding/Construction Information <br /> Butte Valley Construction was shown the site on September 6 h, 2022 in order to obtain a bid for reclamation <br /> work. The bid was considered fair and reasonable and the purchase order for construction was issued on <br /> 8/18/2022. Construction began on 9/6/2022. A separate purchase order in the amount of$2,338.24 was issued on <br /> to Granite Seed Company for purchase of the custom seed mix on 8/24/2022. <br /> Type of Bid Discretionary Purchase <br /> Project Number Contractor Name & Construction Funding <br /> 2023-3516 Address Dates Bond: <br /> Butte Valle Construction $45,638.24 <br /> Y Start: 9/6/2022 <br /> P.O. Box 146 Severance Tax: <br /> Walsenburg CO, 81089 $ 3,500 <br /> End: 9/10/2022 Project Cost <br /> Construction: $46,800 <br /> Seed: $2,338.24 <br /> Construction Work Description <br /> Reclamation of the J&S Farms site included reducing the highwalls, and removing tamarisk, from the shoreline of <br /> the ponds. The highwalls were approximately six to ten (6-10) feet above the groundwater elevation, and <br /> approximately three thousand feet (3,000) in length. (See attached map). <br /> Highwall elimination started approximately fifteen feet back from the edge of the pond. Material was cut to achieve <br /> an overall slope of 3H:1V. The cut material was placed directly into the pond as fill to achieve the specified grade. <br /> It is estimated that approximately five thousand three hundred cubic yards (5,300 yd3) of material was cut to <br /> eliminate the highwalls. <br /> As of05/14/09 <br />