<br /> 6.4.5 EXHIBIT E - Reclamation Plan
<br /> 'Table E-1 - Two Rivers Mining-Regrading Schedule
<br /> Mining-Regrading Schedule Years
<br /> Schedule 1-5 6-10 11-15 16-20 21-25 26-30 31-35
<br /> Area(ac) Area Mined(ac±)
<br /> Central Field
<br /> Center Section 127.1 40.0 40.0 30.0 17.1
<br /> North-East Section 23.2 10.0 13.2
<br /> West Section 30.5 9.7 20.8
<br /> North West Field 53.3 19.2 34.1
<br /> Total 234.1 40.0 40.0 40.0 40.0 40.0 34.1
<br /> Length(ft) Pit wall Created(ft±)
<br /> Central Field 15,074 5,110 3,360 3,360 3,244
<br /> North West Field 6,830 4,001 2,829
<br /> Total 21,904 5,110 3,360 3,360 3,244 4,001 2,829 0
<br /> Length(ft) Pit wall Regraded(ft±)
<br /> Central Field 15,074 3,360 3,360 3,360 3,360 1,634
<br /> North West Field 6,830 1,040 5,790
<br /> Total 21,904 3,360 3,360 3,360 3,360 2,674 5,790
<br /> Length(ft) Pit wall Remaining(ft±)
<br /> Central Field 15,074 5,110 5,110 5,110 4,994 1,634 0 0
<br /> North West Field 6,830 4,001 5,790 0
<br /> Total 21,904 5,110 5,110 5,110 4,994 5,635 5,790 0
<br /> 6 Adequacy Item 29
<br /> VARRA COMPANIES, INC. TWO RIVERS SAND GRAVEL AND RESERVOIR PROJECT MARCH 2O22
<br /> A REGULAR IMPACT[1121 CONSTRUCTION PERMIT APPLICATION-COLORADO DIVISION OF RECLAMATION WING&SAFETY