Permit No.1978-093
<br /> Company:Pete Lien&Sons
<br /> Mine:Newett Quarry
<br /> By:Michael Golliher,Pete Lien and Sons,Inc.
<br /> Date:August 12,2022
<br /> Total Disturbance 13 6 Acres
<br /> Reclamation Task Guideline 12 Amount Units Cost($)/Unit Cost for Task Explanation Amount Details
<br /> Dozer will reduce blasted material to 2 1 slope,-10%grade,
<br /> Highwall Reduction/Backfill by Dozing Appendix E 6,700 LCY $ 021 /LCY $ 1,407 pushing an average of 150 LF(at most)of travel for each pass.
<br /> 6,700 CY of material
<br /> Highwall Reduction/Backfill by recoveng the Dozer will move stockpile material educe blasted material to 2:1
<br /> topsoil/growth medium stockpile Appendix E 7,000 LCY $ 053 /LCY $ 3,675 slope,an average push of 300 LF(at most)of travel for each
<br /> pass 7,000 CY of material
<br /> Reduce finished product slopes to 3.1 Appendix E 4,850 LCY $ 021 /LCY $ 1,019 Reduce the side slopes of the finished product stockpiles. 1/2
<br /> the volume of the piles,an average of push 150 LF.
<br /> Rip the Pit Floor&Roads Appendix 11 13.60 Acres $ 81617 /Acre $ 11,100 Caterpiller D9T used to scarify the exposed pit floor,stockpile Total Affected acreage
<br /> area and roads
<br /> Rough Grade by Dozer Appendix M 769 Acres $ 6708 /Acre $ 516 D9T Dozer-Dozing used to smooth the area and establish
<br /> through-drainage according to rec plan).
<br /> Slope reduction/reconstruction by Excavator PLS Cost 80.00 Hours $ 12000 /hour $ 9,600 Komatsu PC200 Excavator
<br /> Final Grade Appendix G 1360 Acres $ 7500 /Acre $ 1,020 16M Motor Grader
<br /> Scarify Appendix P 1360 Acres $ 4585 /Acre $ 624 16M Motor Grader
<br /> Topsoil Distribution-Stockpile Area Appendix C 2,000 CY $ 0 725 /CY $ 1,450 Salvage/redistribute approximately 2,000 CY of topsoil/growth
<br /> media from the area
<br /> Revegetation PLS Estimate 1360 Acres $1,400.00 /Acre $ 19,040 Includes grading topsoil,discing,drill seeding,mulching,and seed Total Affected acreage
<br /> Revegetation(50%Failure Rate) 6.80 Acres $1,40000 /Acre $ 9,520
<br /> Mobilization/Demobilization $ 7,500
<br /> Subtotal $ 66,470
<br /> Overhead and Profit 15.0% $ 9,970
<br /> Legal-Engineering-Project Management 5 0% $ 3,323
<br /> Contingency/Misc Items 15.0% $ 9,970 Contractor profit&design,mobilization,unknowns,etc
<br /> Total Bond(to the nearest hundred): $ 89,700 Current bond held by the CO DRMS is$132,228.
<br /> Pete Lien &Sons, Inc. has not recommenced operations because we are still looking for a high value use for the chemical grade limestone at this quarry.
<br /> Historically, lime was produced from this site for the smelters and mines in the Leadville area.
<br /> Limestone this pure also has many other uses such as calcium feed supplement for livestock, rock dust for coal mines and pH remediation for soils with a low pH.
<br /> The most recent sales from this quarry were to the Leadville area along the Arkansas River to raise the pH levels in the soil to acceptable level.
<br /> Because of the potential for supplying these markets,we are hesitant to reclaim the site prior to exhausting all options.
<br /> Mining permits like this are also difficult to obtain, making them a valuable resource that warrants keeping them open.
<br /> Our Rifle Quarry, Permit No. M-1985-038,was actually very similar to this operation. We tried for many years to develop a market for it but we were ultimately unsuccessful.
<br /> In the end, it was reclaimed with an innovative use of pond sludge from the Rifle Falls Fish Hatchery and was approved for full surety release on June 14,2021
<br /> Pete Lien&Sons recognizes the fact that this quarry must be reclaimed if we cannot put it in to operation at the end of this second,five(5)period of temporary cessation.
<br /> We are commited to honoring our obligation to either reclaim this quarry or make it operational and have a proven record for either operating a quarry or reclaiming it.
<br /> Therefore,we ask for consideration to grant a second, five year term for Temporary Cessation.