14 Construction Schedule Information <br /> Construction of the Reagent Room EPF is being performed in accordance with TR-15 and is being <br /> performed in phases as required by Rule 7.3.1 with inspections by DRMS to assess each phase of <br /> construction. Construction QA/QC for the Reagent Room is provided to DRMS during inspections. <br /> Construction and management of the TSFs is being performed in accordance with the Tailings and <br /> Waste Rock Management Plan (Appendix 7). Construction of the five-stage passive mine water <br /> treatment system is complete. <br /> M-2012-032 <br /> Amendment 02 Exhibit U <br /> December 2021 U-30 <br />