Laserfiche WebLink
Ouray Silver Mines Inc. <br /> Technical Revision 15 May 24, 2021 <br /> will be added to the circuit in 2022. A list of tanks described in this section can be found in Table <br /> 1. <br /> All processes from the rod mill downstream are fully wet. From the ball mill discharge tank or <br /> slurry storage tanks slurry is pumped to the 2 Derrick stack sizer screens,which size to p80 of- <br /> 130 micron. These screens replaced the previously used hydro cyclone. Undersized material is <br /> sent to the Pb conditioning tank(1064 gallons).Oversize material is circulated to the ball mill <br /> where it is ground and returned to the screens for sizing. The ball mill reduction takes place in a <br /> wet enclosed ball mill. Sodium metabisulfite(pH control&Zn suppressant),Zinc Sulfate(Zn <br /> suppressant),and Lime(pH adjustment) are introduced into the process in the ball mill. <br /> 3.2 Lead Concentrate <br /> In the Pb conditioning tank,process water,Aerofloat 242,Aerophine 3418A, and MIBC are <br /> added to promote the flotation of Pb and Ag while depressing the Zn to prepare for the <br /> concentrate separation in the lead rougher flotation cell(1320 gallons). The rougher flotation cell <br /> mixes air into the slurry with a rotor so that Pb can adhere to the bubbles and float to the surface. <br /> The rougher flotation cell feeds tailings from the bottom of the cell into Pb rougher scavenger <br /> flotation cells which consist of two sets of tanks(1320 gallons each)with three rotors in each <br /> tank(these tanks will also have two products -a concentrate and a tails). The concentrate goes to <br /> the Pb cleaner flotation cell. The tails from rougher scavenger cells report to the Zn rougher feed. <br /> The concentrate comes off the top of the rougher flotation cell and is fed to the Pb cleaner <br /> flotation cell or Pb cleaner column determined by recovery/concentrate grade. <br /> The slurry then enters Pb cleaner floatation cells(unless bypassed to the Pb cleaner column) <br /> which consist of two banks that both have two tank cells(I"cell 449 gallons,2°d cell 290 <br /> gallons). This step also creates two products—concentrate and tails. The concentrate reports to <br /> the Pb cleaner flotation columns. The tails from bank#1 tank#1 report to the bank#2 tank#1. <br /> Tails from bank#1 tank#2 goes to bank#2 tank#2. Tails from bank#2 tank#1 goes to bank#1 <br /> tank#2. Bank#2 tank#2 tails report to the Zn rougher conditioning tank(which is mislabeled <br /> on drawing 300-PI-004). Concentrate from the Pb cleaner flotation cells reports to the Pb cleaner <br /> column(214 gallons). Like all other tanks in the circuit,the Pb cleaner column creates both a <br /> concentrate and a tail. The tail from the Pb cleaner column are pumped back into the Pb cleaner <br /> flotation tank cell#1. The concentrate from the Pb cleaner column reports to the Pb concentrate <br /> thickener. Process water and flocculant are added to the slurry at the Pb concentrate thickener. <br /> After the Pb concentrate thickener, material reports to the Pb concentrate filter feed tank(933 <br /> gallons). From the Pb concentrate filter feed tank,the concentrate is pumped to the Pb <br /> concentrate filter. Water removed from this step is sent to the filtrate water tank. The Pb <br /> concentrate is sent to a screw conveyor that feeds the bagging system.Once bagged the Pb <br /> concentrate is trucked off site to be sold. An SDS will accompany the bagged product to final <br /> delivery. Offtake is sold to a third party FOB mine warehouse and OSMI does not own the <br /> product once the bags are loaded for shipment. <br /> 3.3 Zinc Concentrate <br /> Page 6 of 12 <br />