Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 10/29/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Sunny, 55 degrees <br /> From: 11:00 To: 13:45 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Sam Lowe) 1 2 Kessler Reclamation 4 9 <br /> Contractor Equipment No. Total Subcontractor Equipment No. Total <br /> Hours Hours <br /> Passenger truck 1 1 Excavator 1 <br /> Grizzly 1 <br /> Loader 1 <br /> Description of Work Performed: <br /> Screening material at the 00 for backfilling along channel alignment <br /> Wayne, Calvin and Sam looked at construction stakes for the energy dissipator; all was clear. <br /> Discussed schedule: backfilling through Tuesday; start into energy dissipator Wednesday. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences, etc.) <br /> Next week will need to order gravel for both below riprap and for the low-flow crossing. <br /> Inspector: Sam Lowe Date: 10/29/2020 <br />