Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 7/30/2020 <br /> Contractor: Ensero Solutions <br /> Shift <br /> Hours Worked Weather: Clear sky <br /> From: 6:00 To: 15:30 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight 1 1.51 Kessler Reclamation 5 6 <br /> Tot <br /> Contractor Equipment No. Totl Hours Subcontractor Equipment No. Hours <br /> Passenger Vehicle 1 4 <br /> Description of Work Performed <br /> Procure lumber materials for concrete forms. <br /> Set up and survey elevations for cutoff wall construction. <br /> Determine height and dimensions of wall. Develop work plan to build concrete forms. <br /> Determine layout and proper slope for PVC drainage pipe. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> Modified form design: Concrete pour to be completed in two lifts due to the excessive height. <br /> Challenge: <br /> The initial plan would require the concrete form to be built in a small area near the shale wall of the <br /> excavation.The logistics were deemed to be excessively tedious and overly time consuming. <br /> Resolution: <br /> The first lift is proposed to be a larger footer to eliminate the need for intricate form work. <br /> The face of the shale wall would be used as the form on the back side of the wall. <br /> Once the footer is poured, the wall form would be constructed per plan on top for the second lift. <br /> Inspector: Tyler Fasenmyer Date: 7/30/2020 <br />