Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 7/27/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Clear sky <br /> From: 7:45 To: 15:15 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No Hours (by Labor Class) No. Hours <br /> Oversight (Isaac) 1 4 Kessler Reclamation 5 6 <br /> Contractor Equipment No. Totl Hours Subcontractor Equipment No. TotHours <br /> General Air Sampler 1 1 Excavator 1 2 <br /> Haul Truck 1 2 <br /> Description of Work Performed <br /> Excavator used to clear path for cement truck to catchment at the top of NWRP <br /> Haul truck used to pace excavated material in temporary storage area outside of the Black Forest <br /> Mine. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences, etc.) <br /> Kessler Reclamation concerned with hiring concrete trucks willing to drive up the hill to pour. <br /> Inspector: Isaac Gonzales Date: 7/27/2020 <br />