Laserfiche WebLink
NEWMONT <br /> GOLDCORA <br /> overall estimated schedule including activity durations for construction, operation, and <br /> reclamation of the Cresson Project. Tables D-2 and D-3 provide the annual sequence of mining <br /> and overburden placement, respectively, in each of the mine areas and OSAs. Actual <br /> development schedules may vary from those presented below and will be reported in the annual <br /> reports to DRMS. <br /> Table D-1. Approximate Time Schedule of Construction, Operations and Reclamation <br /> Activity Duration in Start Year Complete <br /> Years <br /> Install and Maintain Erosion Controls— Mine 29 Continuing 2041 or when <br /> and Overburden Areas revegetation is <br /> established <br /> Clear and Grub Mine Areas 11 When 2022 <br /> needed <br /> Construct Haul Roads 13 When 2025 <br /> needed <br /> Completed in 2016 <br /> Mining and Ore Loading VLF1 1 Continuing but capacity still <br /> available, if needed <br /> Mining and Ore Loading VLF2 10 2016 2025 <br /> Underground Exploration and Mining 9 2019 2025 <br /> Processing of Ore in HG Mill 9 2015 2024 <br /> Crusher and Conveyor Reclamation 1 2026 2026 <br /> Mine and Overburden Storage Area 20 Continuing 2032 <br /> Reclamation <br /> Complete the Leaching of Ore on the VLF1 12 Continuing 2024 <br /> Complete Neutralization of VLF1 6 2031 2037 <br /> Reclaim ADR1 Facilities 2 2039 2041 <br /> VLF1 Reclamation 2 2031 2032 <br /> Complete the Leaching of Ore on the VLF2 17 2016 2033 <br /> Complete Neutralization of VLF2 6 2033 2039 <br /> ADR2 Facilities Reclamation 2 2039 2041 <br /> VLF2 Reclamation 2 2039 2041 <br /> Post Closure Monitoring 5 2041 2046 <br /> Notes 1.Actual mining schedule/sequence may vary due to changing mining or economic conditions. <br /> Cripple Creek&Victor Gold Mining Company Exhibit D <br /> Cresson Project Amendment 13 <br /> 7 <br />