Laserfiche WebLink
Page 5 of 245 <br /> Dozing method: 1.200 (S-BY-S) <br /> Visibility: 0.800 (POOR) <br /> Job efficiency: 0.790 (3 SHIFTS/DAY) <br /> Spoil pile: 0.900 (SSD-FC) <br /> Push gradient: 1.601 (CAT HB) <br /> Altitude: 1.000 (CAT HB) <br /> Material Weight: 0.929 (CAT HB) <br /> Blade type: 1.000 (PAT) <br /> Net correction: 0.7614 <br /> Adjusted unit 627.77 LCY/hr <br /> production: <br /> Adjusted fleet 1255.54 LCY/hr <br /> production: <br /> JOB TIME AND COST <br /> Fleet size: 2 Dozer(s) <br /> Unit cost: $0.581/LCY <br /> Total job time: 40.79 Hours <br /> Total job cost: $29,744 <br />