Laserfiche WebLink
Newmont-Cripple Creek&Victor Gold Mine <br /> Technical Specification No.02200 REV D <br /> Squaw Gulch VLF ■ <br /> Project No.475.0106.006 <br /> March 13,2020 <br /> Liner Fill, the geomembrane shall be removed and CONTRACTOR shall recondition <br /> and recompact the Soil Liner Fill to meet all placement and trimming <br /> SPECIFICATIONS, at no additional cost to CC&V. <br /> 15. CONTRACTOR shall remove all hubs and survey stakes in the Soil Liner Fill and backfill <br /> all holes with MANAGER and CERTIFYING ENGINEER approved moisture- <br /> conditioned Soil Liner Fill or bentonite. Compact with a Proctor hammer or other <br /> suitable device that will achieve a kneading type of compaction and will achieve the <br /> required density. <br /> 16. CONTRACTOR shall verify the final thickness of Soil Liner Fill to determine compliance <br /> with this SPECIFICATION. Thickness verification shall be performed at a minimum <br /> frequency of two measurements per acre using a soil-coring device, unless directed <br /> otherwise by MANAGER. CONTRACTOR shall record as part of the as-built <br /> documentation the location, elevation, and thickness of each Soil Liner Fill <br /> verification test. CQA Monitor will witness all verification measurements. <br /> CONTRACTOR shall backfill all holes with MANAGER and CERTIFYING ENGINEER <br /> approved moisture- conditioned Soil Liner Fill compacted with a Proctor hammer or <br /> other suitable device that will achieve a kneading type of compaction and will achieve <br /> the required density, or bentonite. Areas with deficiencies shall be reworked by <br /> CONTRACTOR, until acceptable measurements are obtained at no additional cost to <br /> CC&V. <br /> 17. If tests indicate the Work does not meet the requirements of the SPECIFICATIONS, <br /> MANAGER and CERTIFYING ENGINEER will establish the extent of the <br /> nonconforming area. The nonconforming area shall be reworked by CONTRACTOR <br /> until acceptable test results are obtained at no additional cost to CC&V <br /> 18. Prior to any geosynthetics being placed on Soil Liner Fill, the area will be tested by <br /> CQA Monitor. No geosynthetics will be allowed to be placed on frozen material, as <br /> defined in Section 3.06, without the area in question being retested by the CQA <br /> Monitor. <br /> H. Drain Cover Fill <br /> 1. Drain Cover Fill shall be placed over the geomembrane in the locations shown on the <br /> DRAWINGS. <br /> 2. Prior to placing the Drain Cover Fill, CONTRACTOR shall verify by visual inspection <br /> that the underlying geosynthetics are free of holes,tears,wrinkles,or foreign objects. <br /> MANAGER and CERTIFYING ENGINEER will inspect the geosynthetic for wrinkles <br /> prior to placement of Drain Cover Fill. As instructed by MANAGER, CONTRACTOR <br /> shall "work out"wrinkles to the satisfaction of MANAGER and CERTIFYING ENGINEER <br /> prior to placement of the Drain Cover Fill. In all cases, wrinkles shall not be of a size <br /> that they could fold back on themselves. Wrinkles greater than one foot shall be <br /> removed and repaired by the INSTALLER. <br /> Page 17 <br />