Newmont-Cripple Creek&Victor Gold Mine <br /> Technical Specification No.02200 REV D <br /> Squaw Gulch VLF ■ <br /> Project No.475.0106.006 <br /> March 13,2020 <br /> A. Stripping of the topsoil shall be done within the entire area of the stripping limits. <br /> B. CONTRACTOR shall excavate and remove topsoil in a manner that will minimize <br /> contamination with other soil horizons, and will take such measures as are necessary to <br /> ensure that the removal of topsoil does not result in erosion or excessive sedimentation. <br /> C. CONTRACTOR shall stockpile topsoil at locations designated by MANAGER. Stored topsoil <br /> shall not be disturbed by mining, leaching operations, or construction activities, and shall <br /> be protected from wind and water erosion, compaction, and contamination. <br /> D. CONTRACTOR shall grade topsoil stockpiles to prevent erosion and ponding of <br /> precipitation in the stockpile areas. The maximum topsoil stockpile height will be <br /> approved by MANAGER.The CONTRACTOR shall protect stockpiled topsoil by an effective <br /> cover of non-noxious, quick- growing, annual, and perennial plants, approved by <br /> MANAGER, which shall be seeded or planted during the first appropriate growing season <br /> after removal. <br /> 3.3. Waste Removal <br /> Waste material is defined as material too wet, too dry, frozen or containing ice or snow, <br /> containing organic or other deleterious matter, having poor characteristics of grading or <br /> compaction, having other characteristics that may result in undesirable settlement or other <br /> movement of the fill, or within the fill, or otherwise not meeting the requirements of the <br /> SPECIFICATIONS, provided that this definition permits drying, water, and any other processing or <br /> reprocessing to make the material stable and suitable prior to incorporating it into the fill as <br /> permitted in the SPECIFICATIONS or by the MANAGER and CERTIFYING ENGINEER. <br /> A. CONTRACTOR shall excavate and remove waste in a manner that will minimize <br /> contamination with other soil horizons. <br /> B. CONTRACTOR shall stockpile removed waste at locations designated by MANAGER <br /> 3.4. Excavation <br /> A. CONTRACTOR shall perform excavation to the lines and grades shown on the DRAWINGS <br /> or as directed by MANAGER. No excavation shall begin until the CONTRACTOR has <br /> provided construction staking for the proposed work. <br /> B. CONTRACTOR shall prevent the disturbance of surrounding areas during excavation. <br /> Where selective excavations are required to obtain materials for Structural Fill and Select <br /> Structural Fill, the material removed from the excavations shall be taken directly to the <br /> fill areas or, if required, stockpiled by material types.The stockpiles shall be approved by <br /> MANAGER. <br /> C. CONTRACTOR shall grade all excavations to ensure grades are maintained to provide <br /> adequate drainage at all times. Work shall be suspended by CONTRACTOR when, in the <br /> Page 7 <br />