MINING PLAN(CONT) EXHIBIT C <br /> ors , a crushing and screening plant, dump trucks and a water <br /> truck. <br /> A large stockpile of specification aggregates will be <br /> created on the site as mining progresses . Once there is an <br /> adequate supply, the processing plant will be moved to another <br /> site and the processed material will be removed as needed. We <br /> expect the mine to operate year-around with periods of inactivity <br /> when adverse weather conditions exist . There may be periods when <br /> no activity takes place on the mine because there is no demand <br /> for material . We cannot estimate how long these periods of <br /> inactivity will be, but may last up to 6 months or more . If the <br /> period extends past 180 days the operator will file for Temporary <br /> Succession. <br /> When topsoil is encountered, it will be stripped and stock- <br /> piled around the perimeter of the site or on the mine floor for <br /> use in reclamation. We will place an average of eight (8) inches <br /> of salvaged topsoil on the mined area. If the soil stockpiles <br /> remain undisturbed for more than one growing season it will be <br /> temporarily seeded using the approved seed mix at a rate of 40 <br /> lbs-pls per acre . <br /> We expect to have 9 . 3 acres ± or less disturbed at any-one- <br /> time . The bond estimate presented on page 26 shows the amount of <br /> land we will disturb at a worse case scenario . As mining pro- <br /> gresses we expect to have no more that 400 feet of vertical <br /> working face that would need shaping at any-one-time . At the end <br /> of each mining session the highwall will be temporarily graded 2h <br /> to lv so little slope grading will be necessary if mining ends <br /> prematurely. A temporary safety berm will be built along the <br /> south side that will serve two purposes on is drive off safety <br /> and the other is to prevent uncontrolled stormwater runoff from <br /> leaving the disturbed area . The floor of the mine will be graded <br /> to preserve the drainage pattern across the site as shown on the <br /> MINING PLAN MAP-EXHIBIT E-2 . <br /> AUSTIN& BETSY CLENNIN - BECKER PIT May 7, 2020 <br /> 23 <br />