BACKFILL EXISTING
<br />TRENCH WITH NATIVE
<br />MATERIALS
<br />.....................
<br />VARIES
<br />f
<br />J
<br />J
<br />a
<br />YP/PV ratio API Std. 13A less than 3
<br />LL -
<br />1.5' TYP.
<br />W
<br />0
<br />SANDY CLAY
<br />Test results for each lot of bentonite must be provided.
<br />2.
<br />Water Specifications
<br />z
<br />pH 6-8
<br />OVERBURDEN
<br />3,�5,
<br />Z
<br />Z
<br />mI
<br />VARIES
<br />Z
<br />.
<br />VARIES ASTM C33-7
<br />3.
<br />Bentonite Slurry General Specifications
<br />D
<br />. . . . . . .
<br />. . . . . . . . . . . .
<br />. . . CONCRETE
<br />mixed and hydrated in slurry hydration ponds. In general, a
<br />. . . . . .
<br />. . . . . . . . . . . . .
<br />AGGREGATE
<br />.
<br />the slurry by weight is required.
<br />4.
<br />lY W
<br />J
<br />Q
<br />than 40 sec
<br />D_ w
<br />V)
<br />3:
<br />FT 50
<br />FTS{
<br />pH 6.5 to 10
<br />°
<br />GRADE
<br />(MIN)
<br />at least once per batch of slurry. The slurry must be further
<br />tested after placement in the trench. The tests conducted are for
<br />viscosity, density, sand content, and pH. Two sets of tests per
<br />Q
<br />shift at two locations in the trench (approximately 2 feet below
<br />the slurry surface and 2 feet above the bottom of the trench)
<br />are required. If the density of the slurry in the trench exceeds 85
<br />pcf the excess solids must be removed by desanding or the slurry
<br />ASTM C33
<br />replaced with fresh slurry. The slurry level must be maintained at
<br />a.
<br />1b
<br />2 feet below the top of the working platform.
<br />CONCRETE SAND
<br />Bentonite Slurry Testing Specifications after Placement
<br />Unit Weight 1.03 to 1.40 gm/cm3
<br />4720
<br />rr
<br />(IF REQUIRED)d
<br />volume
<br />VAIES
<br />Soil—Bentonite Backfill Specifications
<br />S—B backfill slump ASTM C 143 1 set per 100 cu. yds.
<br />4700
<br />Slump 2-6 inches
<br />...� ..
<br />a. 4.
<br />S—B backfill gradation 1 set per 300 cu. yds.
<br />4.0'
<br />.
<br />3 inch 100
<br />° a:d a.
<br /># 4 40-80
<br />0
<br />SAND AND GRAVEL
<br />#200 20-40
<br />d °
<br />Minimum Plasticity Index of 10
<br />4660
<br />ALLUVIUM
<br />7.
<br />Key Trench and Slurry Wall Cap Specifications
<br />a
<br />During excavation, soundings should be obtained to determine the
<br />elevations of the top of the key layer, the bottom of the
<br />c0
<br />,�
<br />lip -
<br />Oq �
<br />05'
<br />00 O —
<br />� N
<br />1.5
<br />da.
<br />�(TYP.). �. d
<br />:.
<br />(TYP.)
<br />cD
<br />W
<br />C0 co
<br />CO c0
<br />tf) co
<br />C0 co
<br />��
<br />TYP.
<br />Q0 (.4
<br />(0 co
<br />C0 co
<br />It
<br />0) r
<br />U-) co
<br />C0 W
<br />��
<br />N r`
<br />q- O
<br />C0 co
<br />U-) !`-�
<br />N co
<br />C0 co
<br />O r`
<br />00
<br />C0 co
<br />0 0
<br />Ln co
<br />�
<br />O
<br />U)
<br />1q-
<br />4600
<br />3'
<br />,t
<br />�r
<br />is removed after settlement (approximately 2 weeks) and replaced
<br />with a compacted clay cover over the completed slurry wall.
<br />8.
<br />Post Construction Testing
<br />4580
<br />4'
<br />PERIMETER DRAIN
<br />DETAIL (TYPICAL
<br />SECTION
<br />IF REQUIRED)
<br />4720
<br />4700
<br />4660
<br />4640
<br />4620
<br />4600
<br />0+00 0+50 1+00 1+50 2+00 2+50 3+00
<br />Slope - W -E
<br />4720
<br />4720 4700
<br />4700 4680
<br />4680 4660
<br />4660 4640
<br />4640 4620
<br />4620 4600
<br />4600 4580
<br />VARIES
<br />Bentonite Specifications
<br />J
<br />J
<br />a
<br />YP/PV ratio API Std. 13A less than 3
<br />LL -
<br />Filtrate Loss less than 15 cm3
<br />W
<br />0
<br />J
<br />Test results for each lot of bentonite must be provided.
<br />2.
<br />Water Specifications
<br />z
<br />pH 6-8
<br />Hardness less than 200 ppm
<br />Z
<br />Z
<br />mI
<br />VARIES
<br />Z
<br />�
<br />Chloride report
<br />3.
<br />Bentonite Slurry General Specifications
<br />D
<br />The initial bentonite slurry must be tested prior to placement in
<br />the trench. The slurry may be mixed in high shear mixers or
<br />mixed and hydrated in slurry hydration ponds. In general, a
<br />minimum hydration time of 8 hours will allow the bentonite slurry
<br />J
<br />U)
<br />J
<br />the slurry by weight is required.
<br />4.
<br />lY W
<br />J
<br />Q
<br />than 40 sec
<br />D_ w
<br />V)
<br />3:
<br />FT 50
<br />FTS{
<br />pH 6.5 to 10
<br />GRADE
<br />�50
<br />at least once per batch of slurry. The slurry must be further
<br />tested after placement in the trench. The tests conducted are for
<br />viscosity, density, sand content, and pH. Two sets of tests per
<br />Q
<br />shift at two locations in the trench (approximately 2 feet below
<br />the slurry surface and 2 feet above the bottom of the trench)
<br />are required. If the density of the slurry in the trench exceeds 85
<br />pcf the excess solids must be removed by desanding or the slurry
<br />replaced with fresh slurry. The slurry level must be maintained at
<br />least 3 feet above the ground water elevation and no more than
<br />1b
<br />2 feet below the top of the working platform.
<br />5.
<br />Bentonite Slurry Testing Specifications after Placement
<br />Unit Weight 1.03 to 1.40 gm/cm3
<br />4720
<br />rr
<br />volume
<br />PROPOSED
<br />Soil—Bentonite Backfill Specifications
<br />S—B backfill slump ASTM C 143 1 set per 100 cu. yds.
<br />4700
<br />Slump 2-6 inches
<br />S—B backfill gradation 1 set per 300 cu. yds.
<br />GRADE
<br />Screen (US Standard) Percent by Dry Weight
<br />3 inch 100
<br />4680
<br /># 4 40-80
<br />0
<br />rr
<br />#200 20-40
<br />Minimum Plasticity Index of 10
<br />4660
<br />7.
<br />Key Trench and Slurry Wall Cap Specifications
<br />During excavation, soundings should be obtained to determine the
<br />elevations of the top of the key layer, the bottom of the
<br />c0
<br />,�
<br />c0 Lq
<br />Oq �
<br />U) rn
<br />00 O —
<br />� N
<br />!`,�
<br />,n
<br />trench bottom should be cleaned, as a minimum, at the beginning
<br />N
<br />co
<br />CO co
<br />cD
<br />W
<br />C0 co
<br />CO c0
<br />tf) co
<br />C0 co
<br />��
<br />U) Q0
<br />(0 co
<br />C0 co
<br />��
<br />Q0 (.4
<br />(0 co
<br />C0 co
<br />It
<br />0) r
<br />U-) co
<br />C0 W
<br />��
<br />N r`
<br />q- O
<br />C0 co
<br />U-) !`-�
<br />N co
<br />C0 co
<br />O r`
<br />00
<br />C0 co
<br />0 0
<br />Ln co
<br />�
<br />O
<br />U)
<br />1q-
<br />4600
<br />�
<br />,t
<br />�r
<br />is removed after settlement (approximately 2 weeks) and replaced
<br />with a compacted clay cover over the completed slurry wall.
<br />8.
<br />Post Construction Testing
<br />4580
<br />Post construction testing will be conducted in accordance with the
<br />"Colorado State Engineer's Office."
<br />25 FT
<br />9.
<br />Above specifications (notes 1-8) are provided as a general
<br />LO
<br />guideline for permitting purposes. Final specifications and design
<br />EXISTING
<br />50 FT
<br />50
<br />FT
<br />GRADE
<br />RESERVOIR
<br />v'
<br />O.
<br />PROPOSED
<br />GRADE
<br />�
<br />I�
<br />N
<br />M
<br />LO
<br />N
<br />r-
<br />o,
<br />c0
<br />—
<br />0
<br />,d-Cq
<br />0
<br />N1`,�
<br />c0
<br />N
<br />O
<br />O
<br />0
<br />0
<br />0
<br />0
<br />(0
<br />N
<br />rM
<br />rn
<br />r-
<br />r,
<br />N
<br />n0
<br />N
<br />O 0
<br />I` o
<br />M
<br />U)
<br />0
<br />0(D
<br />(0
<br />Ln
<br />0(
<br />0
<br />U-)
<br />;I-
<br />N
<br />0+00 0+50 1+00 1+50 2+00 2+50 3+00
<br />Slope - W -E
<br />4720
<br />4720 4700
<br />4700 4680
<br />4680 4660
<br />4660 4640
<br />4640 4620
<br />4620 4600
<br />4600 4580
<br />%\ NATIVE
<br />`MATERIAL
<br />OVERBURDEN AND TOPSOIL
<br />BACKFILL ALL DISTURBED AREAS
<br />DOWN TO WATER SURFACE
<br />WATER SURFACE ...
<br />TYPICAL BACKFILL SECTION
<br />N.T.S.
<br />VARIES
<br />Bentonite Specifications
<br />J
<br />J
<br />a
<br />YP/PV ratio API Std. 13A less than 3
<br />LL -
<br />Filtrate Loss less than 15 cm3
<br />0
<br />JT -Derr
<br />Test results for each lot of bentonite must be provided.
<br />2.
<br />Water Specifications
<br />z
<br />pH 6-8
<br />Hardness less than 200 ppm
<br />Z
<br />Z
<br />mI
<br />VARIES
<br />J
<br />�
<br />Chloride report
<br />3.
<br />Bentonite Slurry General Specifications
<br />D
<br />The initial bentonite slurry must be tested prior to placement in
<br />the trench. The slurry may be mixed in high shear mixers or
<br />mixed and hydrated in slurry hydration ponds. In general, a
<br />minimum hydration time of 8 hours will allow the bentonite slurry
<br />J
<br />U)
<br />J
<br />the slurry by weight is required.
<br />4.
<br />lY W
<br />J
<br />Q
<br />than 40 sec
<br />D_ w
<br />V)
<br />3:
<br />FT 50
<br />FTS{
<br />%\ NATIVE
<br />`MATERIAL
<br />OVERBURDEN AND TOPSOIL
<br />BACKFILL ALL DISTURBED AREAS
<br />DOWN TO WATER SURFACE
<br />WATER SURFACE ...
<br />TYPICAL BACKFILL SECTION
<br />N.T.S.
<br />3+50 4+00 4+50 5+00 0+00 0+50 1+00 1+50 2+00 2+50 3+00
<br />Slope - S -N
<br />SLURRY WALL MOTES:
<br />1.
<br />Bentonite Specifications
<br />J
<br />J
<br />a
<br />YP/PV ratio API Std. 13A less than 3
<br />Viscometer greater than 30
<br />Filtrate Loss less than 15 cm3
<br />Moisture Content ASTM D 2216 less than 10 percent
<br />JT -Derr
<br />Test results for each lot of bentonite must be provided.
<br />2.
<br />Water Specifications
<br />3J3
<br />pH 6-8
<br />Hardness less than 200 ppm
<br />Total Dissolved Solids less than 500ppm
<br />Oil, organics, acids, alkali less than 50 ppm each
<br />Chloride report
<br />3.
<br />Bentonite Slurry General Specifications
<br />D
<br />The initial bentonite slurry must be tested prior to placement in
<br />the trench. The slurry may be mixed in high shear mixers or
<br />mixed and hydrated in slurry hydration ponds. In general, a
<br />minimum hydration time of 8 hours will allow the bentonite slurry
<br />J
<br />U)
<br />the slurry by weight is required.
<br />4.
<br />Bentonite Slurry Testing Specifications before Placement
<br />Viscosity Measured w/ Marsh Funnel (API RP 1313-1) less
<br />than 40 sec
<br />Density less than 64 pcf
<br />EXISTING
<br />FT 50
<br />FTS{
<br />pH 6.5 to 10
<br />GRADE
<br />�50
<br />at least once per batch of slurry. The slurry must be further
<br />tested after placement in the trench. The tests conducted are for
<br />viscosity, density, sand content, and pH. Two sets of tests per
<br />shift at two locations in the trench (approximately 2 feet below
<br />the slurry surface and 2 feet above the bottom of the trench)
<br />are required. If the density of the slurry in the trench exceeds 85
<br />pcf the excess solids must be removed by desanding or the slurry
<br />replaced with fresh slurry. The slurry level must be maintained at
<br />least 3 feet above the ground water elevation and no more than
<br />1b
<br />2 feet below the top of the working platform.
<br />5.
<br />Bentonite Slurry Testing Specifications after Placement
<br />Unit Weight 1.03 to 1.40 gm/cm3
<br />4720
<br />Sand Content ASTM D 4381-84(1993)e10 to 20 percent by
<br />volume
<br />PROPOSED
<br />Soil—Bentonite Backfill Specifications
<br />S—B backfill slump ASTM C 143 1 set per 100 cu. yds.
<br />4700
<br />Slump 2-6 inches
<br />S—B backfill gradation 1 set per 300 cu. yds.
<br />GRADE
<br />Screen (US Standard) Percent by Dry Weight
<br />3 inch 100
<br />4680
<br /># 4 40-80
<br />#40 25-60
<br />#200 20-40
<br />Minimum Plasticity Index of 10
<br />4660
<br />7.
<br />Key Trench and Slurry Wall Cap Specifications
<br />During excavation, soundings should be obtained to determine the
<br />elevations of the top of the key layer, the bottom of the
<br />c0
<br />,�
<br />c0 Lq
<br />Oq �
<br />U) rn
<br />00 O —
<br />� N
<br />!`,�
<br />,n
<br />trench bottom should be cleaned, as a minimum, at the beginning
<br />N
<br />co
<br />CO co
<br />cD
<br />W
<br />C0 co
<br />CO c0
<br />tf) co
<br />C0 co
<br />��
<br />U) Q0
<br />(0 co
<br />C0 co
<br />��
<br />Q0 (.4
<br />(0 co
<br />C0 co
<br />It
<br />0) r
<br />U-) co
<br />C0 W
<br />��
<br />N r`
<br />q- O
<br />C0 co
<br />U-) !`-�
<br />N co
<br />C0 co
<br />O r`
<br />00
<br />C0 co
<br />0 0
<br />Ln co
<br />�
<br />�
<br />or other observations will be used to assure that the slurry wall
<br />1q-
<br />4600
<br />�
<br />,t
<br />�r
<br />3+50 4+00 4+50 5+00 0+00 0+50 1+00 1+50 2+00 2+50 3+00
<br />Slope - S -N
<br />SLURRY WALL MOTES:
<br />1.
<br />Bentonite Specifications
<br />YP/PV ratio API Std. 13A less than 3
<br />Viscometer greater than 30
<br />Filtrate Loss less than 15 cm3
<br />Moisture Content ASTM D 2216 less than 10 percent
<br />JT -Derr
<br />Test results for each lot of bentonite must be provided.
<br />2.
<br />Water Specifications
<br />3J3
<br />pH 6-8
<br />Hardness less than 200 ppm
<br />Total Dissolved Solids less than 500ppm
<br />Oil, organics, acids, alkali less than 50 ppm each
<br />Chloride report
<br />3.
<br />Bentonite Slurry General Specifications
<br />The initial bentonite slurry must be tested prior to placement in
<br />the trench. The slurry may be mixed in high shear mixers or
<br />mixed and hydrated in slurry hydration ponds. In general, a
<br />minimum hydration time of 8 hours will allow the bentonite slurry
<br />to meet all criteria. A minimum bentonite content of 6 percent in
<br />the slurry by weight is required.
<br />4.
<br />Bentonite Slurry Testing Specifications before Placement
<br />Viscosity Measured w/ Marsh Funnel (API RP 1313-1) less
<br />than 40 sec
<br />Density less than 64 pcf
<br />Filtrate Loss less than 20 cm3
<br />pH 6.5 to 10
<br />The tests listed above should be run 1 or 2 times per shift and
<br />at least once per batch of slurry. The slurry must be further
<br />tested after placement in the trench. The tests conducted are for
<br />viscosity, density, sand content, and pH. Two sets of tests per
<br />shift at two locations in the trench (approximately 2 feet below
<br />the slurry surface and 2 feet above the bottom of the trench)
<br />are required. If the density of the slurry in the trench exceeds 85
<br />pcf the excess solids must be removed by desanding or the slurry
<br />replaced with fresh slurry. The slurry level must be maintained at
<br />least 3 feet above the ground water elevation and no more than
<br />2 feet below the top of the working platform.
<br />5.
<br />Bentonite Slurry Testing Specifications after Placement
<br />Unit Weight 1.03 to 1.40 gm/cm3
<br />4720
<br />Sand Content ASTM D 4381-84(1993)e10 to 20 percent by
<br />volume
<br />6.
<br />Soil—Bentonite Backfill Specifications
<br />S—B backfill slump ASTM C 143 1 set per 100 cu. yds.
<br />4700
<br />Slump 2-6 inches
<br />S—B backfill gradation 1 set per 300 cu. yds.
<br />Screen (US Standard) Percent by Dry Weight
<br />3 inch 100
<br />4680
<br /># 4 40-80
<br />#40 25-60
<br />#200 20-40
<br />Minimum Plasticity Index of 10
<br />4660
<br />7.
<br />Key Trench and Slurry Wall Cap Specifications
<br />During excavation, soundings should be obtained to determine the
<br />elevations of the top of the key layer, the bottom of the
<br />excavation, and the bottom of the trench prior to backfilling. If
<br />sediments in excess of 2 inches have accumulated it is necessary
<br />4640
<br />to clean the trench bottom by airlift pumps or excavation
<br />equipment to remove the sand and sediment that has settled. The
<br />trench bottom should be cleaned, as a minimum, at the beginning
<br />of each shift. Soundings should be obtained approximately every
<br />20 feet.
<br />4620
<br />Adequate keying in the S—B backfill to an impermeable layer at
<br />the base of the wall will be required and specified in the final
<br />design report for the slurry wall. The design documents will include
<br />a description of the key in layer and describe how trench cuttings
<br />or other observations will be used to assure that the slurry wall
<br />will be adequately keyed. Temporary slurry wall protection will be
<br />4600
<br />required in the form of a noncompacted soil cover placed within
<br />one day over each backfilled 100 foot reach. The temporary cover
<br />is removed after settlement (approximately 2 weeks) and replaced
<br />with a compacted clay cover over the completed slurry wall.
<br />8.
<br />Post Construction Testing
<br />4580
<br />Post construction testing will be conducted in accordance with the
<br />"Colorado State Engineer's Office."
<br />N
<br />9.
<br />Above specifications (notes 1-8) are provided as a general
<br />LO
<br />guideline for permitting purposes. Final specifications and design
<br />criteria will be developed during the final design of the slurry wall.
<br />3+50 4+00 4+50 5+00
<br />IL
<br />YI�I�
<br />U � �
<br />m Cn a -
<br />IZJ-
<br />Q N
<br />N
<br />(9
<br />CON L0
<br />00 O U
<br />M
<br />O X a'
<br />U LL
<br />Q p cc -'14 o
<br />L
<br />C J r�
<br />(3) 8�
<br />0 O M
<br />Lr) Li_ O
<br />O
<br />M
<br />U)
<br />N
<br />Z
<br />c�
<br />U)
<br />N
<br />O
<br />c�
<br />_Cz
<br />U
<br />N
<br />rr
<br />J&T Consulting, Inc.
<br />e• ?�,�
<br />Job #
<br />Date
<br />Drawn B
<br />Designed B
<br />Checked B
<br />File
<br />JT -Derr
<br />Scale
<br />Sheet:
<br />3J3
<br />
|