Carter Mine—File M-2020-014 <br /> Reclamation Costs(Direct costs: see note a, below) <br /> Task# Description Equipment/crew Units Unit Cost Total <br /> 1 Backfill "uncompleted" mine openings D6M-type dozer hrs 180. <br /> or final reclamation grading of sites. <br /> Assume 8 hrs per site,x4 sites <br /> (See notes b and c, below) 5,760. <br /> 2 Crew transportation, per diem 4-person crew <br /> 1 day each site,x4 sites 44 pickup day 1000. 4,000. <br /> 3 Seeding disturbed areas ATV w/seeder acre 250. 2,000. <br /> Includes seeder, seed, x8 ac <br /> 4 Mob/demob equipment D6M-type dozer 2,000. <br /> from Gunnison ATV-mounted seeder 500. <br /> Total of Direct Costs........................... $14,260. <br /> ---------------- --------- <br /> ---------------- --------- <br /> Notes: <br /> a. The figures above do not include indirect costs of DRMS contract administration,contractor <br /> profit, etc. <br /> b. Since each "completed" structure at an underground opening will remain as a permanent <br /> feature, only"uncompleted" work at an opening will require bonding to "close." Due to the <br /> step-wise method of constructing secure, permanent openings, and their permanency on the <br /> site,the adit or shaft dimensions given in another attachment are not relevant to closure costs. <br /> c. All sites with "completed" mine openings that require no further closure earthwork should <br /> remain bonded until all other final reclamation earthwork is completed,and bond reduction is <br /> approved. <br />