Reclamation Cost Estimate Update(12/2/2019)-Henderson Mine and Mill <br /> DEMOLITION Material List for Reclamation Cost Model <br /> Material Cost/Unit Materials Units Source Section <br /> steel $ 0.28 cuft RSMeans 2019 0241 16.13 0020 <br /> concrete floor $ 0.58 sgft RSMeans 2019 0241 16.17 0240 <br /> concrete footing $ 9.71 LF RSMeans 2019 0241 16.17 1000 <br /> asphalt $ 4.31 sgyd RSMeans 2019 0241 13.17 5010 <br /> pipe grouting $ 31.00 cult RSMeans 2019 31 73 13.10 0800 <br /> landfill fee $ 0.68 EA 1%x demolition quantities <br /> 72"+dia.CMP $ 49.00 LF RSMeans 2019 0241 13.40 0200 <br /> steel bridge $ 12.15 sqft RSMeans 2019 0241 16.33 0200 <br /> power poles,x-arms $ 316.50 EA RSMeans 2019 0241 13.80 0100,0300 <br /> TDL concrete pipe $ 36.25 LF RSMeans 2019 0241 13.38 0100 <br /> Overland conveyor $ 0.33 sgft RSMeans 2019 05 05 05.10 0500 <br />