November 19, 2019 <br /> 2.0 Critical Construction Periods <br /> 2.1 Removal of All Organic Material and Topsoil <br /> Topsoil and organic material removal activities were not conducted during the quarter. <br /> 2.2 Placement of Underdrainage Systems <br /> The underdrainage system was completed in the first quarter of 2010; additional work on <br /> this system is not anticipated. During the time of the inspection, there was approximately <br /> a quarter of a gallon per minute of water flow. (Photograph 4). <br /> 2.3 Installation of Surface Drainage Systems <br /> Both the north and south surface drains were inspected (Photographs 5 and 6). At the <br /> time of the inspection there was no water flow. <br /> 2.4 Placement and Compaction of Fill Materials <br /> There was no placement of material or contour work done on the fill this quarter. All of <br /> the required material for the fill has been placed and compacted. It's anticipated there will <br /> be no more additional fill material placed on the fill. <br /> Photograph 7 depicts the west facing slope of the fill in the area where the slope of the fill <br /> is at 31-1: 1 V. <br /> 4 . <br /> �—�c•_ ' •, .-fir � K�'�'� � f a ' - - w 1 r r <br /> Photograph 4: Water from the Underdrainage System(1111912019) <br /> 4 <br />