Exhibit D Skull Creek Sand Project <br /> Mining & Backfill Sequence <br /> Prior to mining, all recoverable soils within the affected area will first be salvaged (between 2"- <br /> 6") and stored in windrow stockpiles surrounding the various operational areas as depicted on <br /> Map D-3. Mining will then commence by excavation of the exposed Dakota outcrop within Pit <br /> E-1. Once the outcrop has been removed, alternating blocks of overburden and Dakota <br /> Sandstone will be excavated until the pit bottom is reached. Access to the pit bottom will be <br /> accomplished by temporary ramps built into the progressing pit highwall to the west. <br /> Overburden spoil from Pit E-1 will be hauled out of the pit and placed on the SPRS for eventual <br /> rehandle and backfill into the final pit void of Pit E-5. Following the completion of Pit E-1, <br /> concurrent in-pit backfill will be utilized to avoid ex-pit haulage and to expedite reclamation. <br /> Once concurrent backfill has begun, each successive pit will be mined from East to West in the <br /> same manner with the overburden being placed in the previously mined pits up to the designed <br /> final reclamation topography (See Exhibit E). When mining of Pit E-5 is complete, the SPRS will <br /> be fully re-excavated and hauled back to the pit for final reclamation. <br /> Map D-1 and Table D-2 below also depict the approximate timing and production for full <br /> excavation of pits E-1 to E-5. This timing assumes a first year at half capacity and a second year <br /> at full production. <br /> Table D-2. Quarterly Production Forecast <br /> Recoverable <br /> Plan Sand Plan Sand Overburden Komatsu Strip Ratio(CY OB/ <br /> Year Quarter Months Sand @ 80% (tons) (CY) (CY) 650 OB(CY) tons Sand) <br /> (tons) <br /> 1 1 Jan-Mar 138,928 173,660 93,896 383,867 383,867 2.2: 1 <br /> 11 2 Apr-Jun 138,919 1 173,648 1 93,889 383,842 1 383,842 1 2.2:1 <br /> 11 3 Jul -Sep 139,074 173,843 93,995 389,011 389,011 2.2:1 <br /> 11 4 Oct- Dec 129,157 161,446 87,292 395,711 395,711 2.5:1 <br /> Subtotal 546,078 682,597 369,071 1,552,431 1,552,431 2.3:1 <br /> 2 1 Jan- Mar 225,465 281,831 152,382 787,379 787,379 2.8:1 <br /> 2 2 Apr-Jun 173,505 216,881 117,265 838,210 838,210 3.9:1 <br /> 2 3 Jul -Sep 297,873 372,342 201,320 764,691 764,691 2.1:1 <br /> 21 4 Oct- Dec 256,039 320,049 173,046 620,651 620,651 1.9: 1 <br /> Subtotal 952,8821 1,191,1021 644,013 1 3,010,931 3,010,931 2.5:1 <br /> Grand Total 1,498,959 1,873,699 1 1,013,084 1 4,563,362 4,563,362 2.4:1 <br /> Product Streams <br /> Dakota Sandstone is the primary and only expected extracted commodity, which will be mined <br /> and shipped to a processing facility for comminution and sizing for eventual use as a frac-sand <br /> 3 <br /> 11/1/2019 <br />